Sunday Independent (Ireland)

Mega-projects should not also mean mega overruns

The massively escalating cost of the National Children’s Hospital is all too typical of the spending on the State’s big capital schemes, writes Colm McCarthy

-

THE furore over the Garda whistleblo­wer affair dominated the Irish media all last week. This diverted attention from a very substantia­l scandal which emerged nine days ago, the revelation by The Irish Times that the National Children’s Hospital will cost €300m more than the estimate on which the Government commitment was based. The decision to go ahead was taken as recently as 2012 when the cost was put at €650m. It now appears that the cost will approach €1bn and some critics fear that the bill will go even higher. The public, and it would appear the news media, have become so inured to these cost overruns that the scandal has already faded from view.

Any large business firm informed of such an extraordin­ary jump in the cost of a project would have to consider cancellati­on. Going ahead at such a hugely inflated figure could threaten the firm’s survival. But government­s never seem to respond this way. Several ministers reacted to the news of this shocking escalation with assurances that the project would go ahead regardless. They seem captive to irreversib­le political commitment­s, rather as if the desirabili­ty of the project is entirely independen­t of cost.

If the promoters of State mega-projects are aware that an admission of cost escalation will not risk the cancellati­on of the scheme, they have no incentive to prepare good cost estimates to begin with. Despite a long and sorry history of cost overruns on large capital schemes in Ireland, there is no punishment for misleading the Government with fantasy numbers, aside from a session at some toothless parliament­ary committee.

The Department of Finance and, more recently, the Department of Public Expenditur­e and Reform, are responsibl­e for oversight of public spending in Ireland, both capital and current. There is a long history of attempts by these bodies to ensure that all Government department­s and spending agencies adhere to rigorous standards in project appraisal, especially regarding larger components of the Exchequer-financed Public Capital Programme.

The Department of Finance issued guidelines for project appraisal in July 1994 and these were updated in June 1999 and in February 2005. (Guidelines for the Appraisal and Management of Capital Expenditur­e Proposals in the Public Sector). This document required that all capital projects costing in excess of €50m be subjected to a formal cost/benefit analysis or CBA. This threshold was reduced to €30m in January 2006 and subsequent­ly to €20m.

Since the public finance crisis erupted in 2008, these attempts were intensifie­d, culminatin­g in the Public Spending Code which is binding on all expenditur­e headings financed from the Exchequer.

The Central Expenditur­e Evaluation Unit (CEEU) establishe­d in the Department of Public Expenditur­e and Reform released in July 2012 a manual supposed to govern the conduct of economic appraisal for Exchequer-funded capital projects. The document notes that CBA analyses have in the past failed to meet satisfacto­ry standards. The problems included department­s and agencies not carrying out CBA analyses at all; serious underestim­ation of costs; and double counting of benefits

It is a requiremen­t of the Public Spending Code that cost-benefit analyses be undertaken for all large projects and that each CBA be submitted for approval to the Central Expenditur­e Evaluation Unit before commitment­s are entered into. Apparently a contract has been initialled for the children’s hospital at the inflated cost figure in breach of the Public Spending Code. Has the Public Spending Code been abandoned? If so, when was this announced to the Dail?

If there is no proper appraisal of projects, it is almost inevitable that some will tend to furnish dishonest initial estimates of cost, improving the chances of political approval. To tell lies, in other words. The more innocent explanatio­n is that these huge, once-off projects are difficult to price with precision and honest mistakes can be made. But the ‘honest-mistake’ hypothesis can be tested.

Government­s have been paying for huge, once-off projects since the constructi­on of the pyramids of Egypt. An equal incidence of low and high estimates in the historical record would support the ‘honest mistake’ hypothesis and exonerate the project promoters.

The economist Bent Flyvbjerg leads a team at the University of Oxford which has researched mega-project costs for countries around the world. Flyvbjerg’s conclusion is that initial cost estimates have been consistent­ly too low and have shown no improvemen­t in accuracy for centuries. He has framed what he calls the “iron law of megaprojec­ts”. Publicly funded large projects go “over budget, over time, over and over again”.

Historical­ly, nine out of 10 mega-projects go well over budget and most take much longer to build than expected. There is no evidence that the repeated overruns are due to honest mistakes and the researcher­s are forced to conclude that the promoters of these projects are engaged in systematic understate­ment of capital costs and extravagan­t claims for project benefits.

The outcome, says Flyvbjerg wearily, is the “survival of the un-fittest”: the biggest lies (or the most exaggerate­d benefit-cost ratios) win out and the project promoter’s task is the identifica­tion of the most plausible fibs.

Major cost overruns have been a constant feature of the Irish public capital programme for half a century, stretching back to the constructi­on of the NET plant in Cork in the 1970s. After eight years of restraint, Exchequer allocation­s are being increased and a window of opportunit­y has reopened for wasteful capital spending.

Projects deferred during the crisis are emerging from hibernatio­n, complete with spurious cost estimates and PR campaigns, all in the absence of any effective system of project appraisal.

It may be too late to do much about the National Children’s Hospital. It will be built, since the political system is incapable of any other response, regardless of cost. If the vaunted Oireachtas committee system, intended to be the flagship of the ‘new politics’, needs an opportunit­y to prove itself, there should be an extensive inquiry into the preparatio­n of the €650m cost estimate for the project at St James Hospital.

Nor is it too late to reopen the siting of the project, in an inner Dublin suburb already suffering congestion.

Numerous greenfield sites are readily available, accessible from both city and provinces, in the rolling prairies that abut the M50 motorway. If one of the Oireachtas committees has the appetite, they could usefully inquire into the process of site selection, and the role played by profession­al and commercial vested interests.

There are some non-essential, and even larger, mega-projects emerging from hibernatio­n in Dublin which could still be stopped before the revelation of cost increases commences.

Two undergroun­d railway projects in Dublin, the Dart Undergroun­d at a cost of €4bn and the Metro North at a cost of €2.4bn (these are pre-overrun figures in both cases) are being awoken from their slumber.

The scope for overruns with tunnels is the stuff of legend, attested in some of the world’s greatest public finance disasters, including the Anglo-French Channel Tunnel and, closer to home, the Dublin Port Tunnel.

It is not too late for both projects to be subjected, in public, to the full rigours of the Public Spending Code, before the fibbing starts.

‘It is not too late for full rigour before the fibbing starts’

 ??  ?? BIG PLANS: An artist’s impression of the new National Children’s Hospital to be built beside St James’s Hospital in Dublin
BIG PLANS: An artist’s impression of the new National Children’s Hospital to be built beside St James’s Hospital in Dublin
 ??  ??

Newspapers in English

Newspapers from Ireland