The Corkman

Public warned to expect ‘a lot of disruption’ during works on Mallow boardwalk project

- BILL BROWNE

A SENIOR Cork County Council official has warned that traffic disruption in Mallow would be inevitable once work commences on the constructi­on of the multi-million boardwalk adjacent to the town bridge.

Speaking to councillor­s at the February meeting of the Council’s Kanturk/Mallow committee, senior engineer Jim Moloney said the project is currently in the final stages of the design phase.

“It is hoped this will be complete shortly and that a public meeting in relation to the project will be held in Mallow some time during February, at a date yet to be decided,” said Mr Moloney.

“Councillor­s will be fully briefed on progress before the meeting,” he said.

In October of last year, The Corkman revealed that the €1 million EU grant allocated for the creation of a regional arts centre in Mallow Town Hall had been reallocate­d to the boardwalk project.

This was after it emerged that the cost of the town hall project had spiralled to more than €5 million, with the council conceding that the project could not be completed within the allocated timeframe for the grant to be spent.

On the advice of the Southern Assembly, it was decided that the funding would be switched to the boardwalk project to ensure it was not lost to the town.

Granted Part Eight planning permission more than seven years ago, the project will incorporat­e the constructi­on of a new walkway on the western side of the bridge; the creation of a third traffic lane; the demolition of the public toilet block; and the relocation of the existing memorial on the bridge.

It is envisaged that the project, which will cost in the region of €2.1 million to undertake, will go to tender over the coming weeks, with constructi­on staring in the spring and set to be completed before the end of the year.

Speaking at last Friday’s meeting, Cllr Melissa Mullane (SF) asked if a schedule of works had been drawn up for the project and, if so, had provision been made for the a lot of the works to be undertaken at night to minimise traffic congestion.

“That is certainly something that should be investigat­ed. There is already a high level of traffic disruption in Mallow at certain times of the day, which has resulted in a lot of negativity around the town,” she said.

In reply, Mr Moloney said the authority was aware of the problems the works would cause, and these concerns had already been passed on to the design office and consultant­s.

“However, the nature of the work involved means that there will be a lot of disruption, regardless of whether the works are done at night or during the day,” he warned.

Cllr Mullane said that while she understood this, there were certain jobs, such as road resurfacin­g, that she feels could easily be done overnight.

“This seems to be to be a very logical thing to do in order to minimise disruption and must be looked into,” she said.

Cllr Gearoid Murphy (FF) said his colleague had made an important point and it should be stressed to the contractor­s appointed that, where possible, works should be undertaken at night, when traffic levels in Mallow are at their lowest.

 ??  ?? An artist’s impression of how the planned Mallow Boardwalk, which is due to start constructi­on in the spring, will look when completed.
An artist’s impression of how the planned Mallow Boardwalk, which is due to start constructi­on in the spring, will look when completed.

Newspapers in English

Newspapers from Ireland