Wexford People

Foundation­s completed for River Barrow bridge

- By ESTHER HAYDEN

CONTROLLED blasting is still under way along certain parts of the New Ross bypass as work continues.

So far contractor­s, BAM Dragados, have excavated in excess of 1,000,000 tonnes of material to date and are continuing controlled blasting in the Stokestown and Camlin areas. They have also re-commenced blasting recently in the Ryleen/ Lacken area as well as in the Ballymacar area with mainline drainage works commencing in the coming weeks.

For many motorists the biggest sign of the bypass works came with the diversion of the N25 at Ballymacar which has been put in place to allow the constructi­on of the new roundabout on the footprint of the existing N25 while maintainin­g free flow for road users in both directions during constructi­on. Other diversions realignmen­ts that are now in place are at Creakan, Ryleen, Arnestown.

These are to allow the constructi­on of bridge structures on local roads and Stokestown to allow the new road to be constructe­d. Traffic management works on the N25 at Glenmore have also commenced and are expected to last nine months.

All permanent foundation­s for the River Barrow Bridge have now been constructe­d, with the work shifting to the pier stems on the west side of the river. There are number of temporary foundation­s required to support the falsework for the deck.

Piling works to these temporary foundation­s on the east side of the river have commenced with work to the foundation­s following on from these.

Structures for the rest of the project have moved on and the majority of accommodat­ion underpasse­s and watercours­e culverts are either completed or under constructi­on at present. The bridge structures at Creaken and Ryleen have commenced while the one at Arnestown will commence once the local roads are realigned to accommodat­e working space.

Traffic management will be put in place on the R733 (at Camlin) to facilitate stream diversions in late summer and is expected to last four weeks. During this time a stop go system will be operation at certain areas.

The road closure at the Pink Rock has been extended until June 2018.

During the works mentioned above it will be necessary to employ stop/go at the tie-ins to allow the pavement constructi­on.

At the moment work is ongoing on six of the 12 bridges and on 14 of the 15 planned underpasse­s along the bypass. Nine of the 15 widecourse culverts are either completed or under constructi­on and contractor­s are currently working on one of the three retaining walls required.

By October contractor­s hope to finish the bridge at the R7333 and install precast beams at Camlin. It is also expected that the installati­on of precast bridge elements at Creakan and Ryleen will be completed. The pier stems, temporary piers and bridge deck of the Barrow Bridge is also expected to be completed.

 ??  ?? Looking across to
Pink Rock from Dunganstow­n, constructi­on continues on the new bridge across the river Barrow
Looking across to Pink Rock from Dunganstow­n, constructi­on continues on the new bridge across the river Barrow

Newspapers in English

Newspapers from Ireland