Wicklow People

SSE applies for foreshore licence

FORESHORE LICENCE SOUGHT FOR ARKLOW BANK WIND FARM

- By EIMEAR DODD

SSE Renewables has applied for a foreshore licence to carry out investigat­ions at the Arklow Bank Wind Farm and the site of a potential operations base in Arklow.

The company is currently carrying out an ongoing process of assessing Wicklow Port and Arklow Harbour as possible locations for an onshore hub for servicing and maintainin­g the offshore wind farm. A decision on the preferred location has yet been made.

The applicatio­n has been made to the Department of Housing, Planning and Local Government for a licence to carry out surveys to collect informatio­n for the next phase of Arklow Bank Wind Farm project. There are also plans for surveys of potential cable routes, landfall sites and at Arklow Harbour. A wind conditions survey is also proposed.

A SSE Renewables spokespers­on said, ‘SSE Renewables has applied for a Foreshore Licence to carry out site investigat­ions for Arklow Bank Wind Park. The Foreshore Licence will facilitate undertakin­g survey work to support developmen­t activities at the wind farm site, along the cable route and at potential operation bases between now and constructi­on. This survey work is a routine part of the developmen­t process and will add to the existing informatio­n currently held in order to facilitate the ongoing engineerin­g and design of the project, prior to constructi­on.

‘The SSE Renewables project developmen­t team is working intensely on the ongoing design and engineerin­g for the next stage of the project, and this Foreshore Licence applicatio­n is another positive indicator of the progress being made in the developmen­t of Arklow Bank Wind Park Phase 2. Key future milestones in the project programme for the year ahead include securing a grid connection and securing a support contract for low carbon energy from Government under the new Renewables Electricit­y Support Scheme regime, and the project roadmap for both of these milestones is significan­tly advanced and on course.’

According to the applicatio­n documents, the proposed surveys will provide a ‘further level of detail required to inform the initial engineerin­g design of the foundation structions’. The informatio­n would be used to comply a detailed model of the area to support the design of turbines, foundation­s, cables and other equipment.

Investigat­ions proposed include the drilling of boreholes at the potential sites of turbines at the Arklow Bank Wind Farm site. Permission is also sought for the drilling of six boreholes in Arklow Harbour at the potential site of an onshore base. A survey of the wind conditions on the Arklow Bank site wpi;d also be carried out.

The applicatio­n goes on to note that further surveys will be required before the constructi­on of turbines can commence, with a separate foreshore licence to be applied for at a later date.

If the licence is granted, the applicatio­n states that surveys would begin in early 2020 and would be scheduled in the spring and summer months over a threeyear period.

A supporting document compiled by Gavin and Doherty Geosolutio­ns Ltd. notes that the Arklow Harbour survey is estimated to take around two to three weeks, while the wind resource survey could take between one and two years.

Submission­s can be made before January 3, 2020 to the Marine Planning and Foreshore Section, Department of Housing, Planning and Local Government, Newtown Road, Wexford, Co Wexford or foreshore@ housing.gov.ie.

A 99-year foreshore lease was granted in 2002 for a 520 MW offshore wind farm off the coast from Arklow. SSE Renewables has indicated it plans to invest up to €2 million in the second phase of the project. Company representa­tives confirmed to members of Arklow Municipal District in March last that Wicklow and Arklow were being considered as possible sites for the land-based hub.

Newspapers in English

Newspapers from Ireland