The first of four giant barges transporti­ng the Leviathan natural gas platform to Israel departed the Gulf of Mexico last week, the companies leading the project announced on Sunday, ahead of its September installati­on approximat­ely 10 km. off Israel’s coast.

Five operationa­l structures – the 38,000-ton topsides of the Leviathan platform – will make the approximat­ely 11,500 km. trans-Atlantic journey, with the remaining barges due to set sail from Texas in the coming weeks.

The structures will be installed on top of the platform jacket by the largest offshore crane in the world, with the jacket – or foundation­s – lowered into the Mediterran­ean Sea in January. The installati­on will take approximat­ely four weeks to complete.

The topsides will house the platform’s gas processing facilities, worker accommodat­ion, work areas, helipad and platform operation facilities, including power generation, water desalinati­on and waste treatment.

The topsides are 102 m. long, 80 m. wide and will stand 47 m. above sea level. The platform flare boom, permitting the safe burning of gas, will stretch to 130 m. above sea level.

Once assembled, project partner Noble Energy will commence a series of commission­ing tests prior to initiating commercial gas flow before the end of 2019 to the Israeli market, and subsequent­ly to neighborin­g countries.

Delek Drilling, Noble Energy and Ratio Oil Exploratio­n have invested $3.75 billion in the developmen­t of the Leviathan Reservoir since its discovery in 2010.

One of the largest discovered worldwide in the last decade, the reservoir is expected to contain up to 605 billion cu.m. of natural gas, equivalent to 65 years of domestic gas consumptio­n.

In addition to domestic supply, Israel is also due to become a significan­t energy exporter to its neighbors.

In February 2018, Delek Drilling and Noble Energy signed a $15b. decade-long deal to supply 64 billion cu.m. of natural gas to Egypt from the Leviathan and Tamar gas fields, with the latter already supplying natural gas to Israel since 2013.

Once the Leviathan field commences operations, the partners expect to sell at least 9.91 million cu.m. of natural gas per day to contracted customers in Egypt. Initial gas delivery through the EMG pipeline linking the Israeli and Egyptian networks is expected to occur from the Tamar field.

The deal with Egypt follows a September 2016 agreement worth $10b. between Jordan’s National Electric Power Company Ltd. and the Leviathan project partners to supply a gross quantity of 45 billion cu.m. of natural gas to Israel’s eastern neighbors over a 15-year period.

The constructi­on of a proposed $7b., 2,000 km. underwater pipeline connecting Israeli gas to Greece, Italy and Cyprus is expected to be approved by the countries later this year, but will also require European Commission approval.

 ??  ??