NWA will ensure December timeline is met

- jason.cross@gleanerjm.com

NATIONAL WORKS Agency’s communicat­ions manager, Stephen Shaw, said that he plans to ‘hold the feet’ of the contractor­s in the Barbican Road developmen­t project to the fire, to ensure the December 2017 timeline is met.

“One of the key things that we had to do before we got to this place was to acquire properties. We acquired some 30 parcels of land. The amount of money the Government has had to put up to provide for the widening is as much as we are going to be spending to construct the road. We would have spent upwards of $300 million to acquire properties,” he said.

“We intend to hold the contractor­s to books as it relates to how the traffic will flow when constructi­on is on the way. You will not get less than that which you are accustomed to. You are used to two lanes, so two lanes will remain open at all times. The Bustamante Bridge (near Fontana Pharmacy) is being widened to facilitate additional lanes that are to be created. We are to have turning lanes at Birdsucker Avenue. We are going to be signalizin­g Jacks Hill and we are going to be signalizin­g East King’s House Road. The flow is going to be different, so the loop (between Loshusan and the open lot) that you are accustomed to making for years will no longer be,” Shaw explained.

COLLABORAT­IVE EFFORT

He said that various agencies, such as the National Water Commission and the National Works Agency will be working in unison.

The project is funded by a loan of $353 million from the Export-Import Bank of China and is only one of a number of projects in the pipeline to alleviate traffic congestion problems across Kingston and St Andrew.

“If you want to see what Jamaica looks like, Barbican is what you would call the microcosm of Jamaica. Because of that, it is an area that has the potential for significan­t economic expansion. What is holding us back is infrastruc­ture in roads and housing. The studies say that about 26, 000 motor vehicles pass through Barbican Square on a daily basis. Many people complain how much time they lose and how early they have to get up to clear the area,” said Prime Minister Andrew Holness.

“The work that will be done will be to expand the road and eliminate this loop. I gather that private-sector interests are looking at how they can expand, including acquiring the road that will be abandoned, in order to develop this piece of land (the open lot across from Loshusan). That will mean more jobs,” Holness told the gathering.

 ??  ?? Stephen Shaw