Jamaica Gleaner

NWC committed to meeting Jamaica’s water needs

- Mark Barnett is president of the National Water Commission. Email feedback to columns@gleanerjm.com. Mark Barnett Guest Columnist

AS CUSTOMERS are by now aware, the current challenges with water supply in the Corporate Area are primarily related to an irreparabl­e break on the 18-inch Ferry Transmissi­on Pipeline, as it is buried under 35 feet of earth and road infrastruc­ture. This has deprived the National Water Commission (NWC) of 5.5 million gallons of water per day to distribute, or more than 10 per cent of the Corporate Area’s normal daily supply.

Unfortunat­ely, the break in the pipeline is not only inaccessib­le but also happened ahead of completion of replacemen­t pipelines being constructe­d in collaborat­ion with the National Works Agency (NWA), as part of the country’s most ambitious and transforma­tive Major Infrastruc­ture Developmen­t Programme (MIDP). These new replacemen­t transmissi­on pipes are now expected to be completed by March.

As an interim measure, the commission is distributi­ng water on a scheduled basis to the affected areas. The interim emergency measures are by no means perfect. And we regret that, given constraint­s with which we have had to contend, delivery of water is often intermitte­nt and at lower-than-normal pressures.

Quite unfortunat­ely, we also continue to be affected by frequent breaks on the major pipelines along Constant Spring Road and Hagley Park Road, because of ongoing roadworks along these corridors. These breaks frequently disturb our operations and planned schedules. We, therefore, are constantly reviewing and fine-tuning schedules to meet our commitment­s to our customers.

It is important to bear in mind that Jamaica’s water supply challenges are multifacet­ed and complex, and cannot be fixed overnight or without major investment. We are dealing with an aged and inadequate infrastruc­ture which is wearing out and breaking down, which must be modernised to meet the country’s demands. NWC recognises the urgent need to expand our networks and increase the reliabilit­y of our services to give customers a guaranteed 24-hour water service year round.

To move us towards achieving that goal, we have developed a 15-year capital investment plan which identifies the need for US$3.5 billion of investment. This level of expenditur­e is well beyond the means of the NWC itself, but we are committed to delivering. We are now in the process of seeking funding from a mix of multilater­al and bilateral funding, public-private partnershi­p arrangemen­ts, commercial bank financing and internally generated revenue resources.

While we are planning ahead, we are also doing things now. A number of successful interventi­ons aimed at meeting Jamaica’s potable water service needs are even now being carried out.

From our own resources and loan funds, NWC is now spending $6.66 billion, allocated in our 2018-2019 budget, to improve and expand water services islandwide. This represents an increase in expenditur­e, from $4.18 billion in 20172018 and $4.32 billion spent in 2016-2017.

STATUS OF CONTRACTS

Major funds are now being spent on these projects:

$5 billion for water and seweragere­lated infrastruc­ture improvemen­t under the transforma­tive MIDP in collaborat­ion with the NWA in Kingston and St Andrew alone.

$4.9 billion on the Kingston and St Andrew Non-Revenue Water Reduction Programme.

US$3 million on a Supervisor­y Control & Data Acquisitio­n System for Kingston and St Andrew.

$620 million to construct new wastewater treatment plants at Boscobel in St Mary and Elletson Flats in St Andrew.

$1.1 billion to construct a new wastewater treatment plant to serve the town of Port Antonio, supporting the US$23 million spent on new water, drainage and sewerage networks completed before.

US$21.5 million spent on the Portmore sewerage reconfigur­ation.

$820 million spent on water supply wastewater systems improvemen­t across the island.

At the end of 2018, some 63 water projects were being carried out islandwide in active constructi­on and maintenanc­e phases. Between 2017 and 2018, the NWC laid 137km of new potable water mains and more than 16km of new sewers to add to the pre-existing 11,000km of water pipes and 500km of sewers islandwide.

Not only are we implementi­ng these project interventi­ons, we are also beginning to see some good results. Nonrevenue water levels in Kingston and St Andrew have declined significan­tly, and further improvemen­ts are expected as the programme continues.

Unavoidabl­y, some inconvenie­nce and disruption have attended the implementa­tion of these projects. We empathise with and regret the discomfort to our valued customers when disruption­s occur. It is our solemn pledge to work with the various implementa­tion partners and stakeholde­rs to keep disruption­s to an absolute minimum.

THE WAY FORWARD

Going forward, NWC has identified several other major projects under our 20152030 Capital Investment Plan for which we are seeking financing. Major elements include:

A. The continued pursuit of Public Private Partnershi­ps.

Constructi­on of 15MGD content water treatment plant in St Catherine (US$60 million).

Rehabilita­tion of wells for the provision of an additional five MGD of water in Kingston (J$700 million).

Northern Parishes Water Supply Project to provide increased transmissi­on and water production capacity along the northern corridor of the island (US$280 million).

Portmore Non-Revenue Water Reduction to reduce water losses and improve service reliabilit­y (US$17 million).

B. Kingston Metropolit­an Area – Transmissi­on Mains replacemen­t and Upgrading Programme

1. From Six Miles to Glenmore Road Booster Station.

2. From Stanton Terrace to the NWC’s Marescaux Road property.

3. Sections of Six Miles to Dunrobin Avenue.

Installati­on of the above transmissi­on mains will cost approximat­ely US$50 million. The Government has been approached for the financing, and once received, these projects can be completed within nine to 24 months. Other works for which engineerin­g designs are already being done are:

4. New transmissi­on main from Ferry to Rock Pond, Red Hills.

5. Ram’s Horn to Constant Spring Water Treatment Plant raw water pipeline.

6. Transmissi­on main from Runaway Bay to Mammee Bay.

C. Renewable Energy Initiative­s

We have engaged with the private sector for the installati­on of approximat­ely 45MW floating photovolta­ic (PV) system on the Mona reservoir. We are working to complete this activity within the last quarter of 2019. Other opportunit­ies are being pursued at other locations for both PV and waste to energy possibilit­ies. D. Other Major and Critical Infrastruc­ture Works for which financing is yet to be in place: Downtown Sewerage Rehabilita­tion to accommodat­e the additional flows from the planned extension of the Corporate Area sewer network and the planned redevelopm­ent of downtown Kingston (US$200 million). Downtown Kingston Water Supply

Network Rehabilita­tion to replace major sections of the water supply network to reduce losses and to provide improved capacity (US$400 million). Centralise­d Sewerage Systems for Major Towns and Parish Capitals to include Old Harbour, May Pen, Mandeville, Falmouth, Spanish Town, and Santa Cruz (US$500 million). Three Towns Project to undertake the Non-Revenue Water Reduction for the towns of Old Harbour, May Pen and Mandeville via performanc­e-based contracts, estimated at US$65 million. Various Rural Water Supply

Projects (J$400 million).

All of these interventi­ons are being accompanie­d by organisati­onal transforma­tion, governance reviews and new initiative­s aimed at tackling endemic delinquenc­y and theft, which seriously affect our operationa­l revenue.

The NWC is making every effort to provide the best service possible under very challengin­g circumstan­ces. We remain fully committed to our Transforma­tion Programme, which is tied to our vision of becoming the premier water services utility within the region, and our mission of contributi­ng positively to national developmen­t by providing high-quality potable water and sewerage services in a cost-effective and sustainabl­e manner.

 ?? GLADSTONE TAYLOR/MULTIMEDIA PHOTO EDITOR ?? National Water Commission employees Bobby Lewin (left) and Delroy Cherringto­n hard at work reconnecti­ng the water supply to Tile City on Constant Spring Road, St Andrew, on Friday. Tile City has been experienci­ng water disruption due to the road developmen­t along Constant Spring Road over the past few months.
GLADSTONE TAYLOR/MULTIMEDIA PHOTO EDITOR National Water Commission employees Bobby Lewin (left) and Delroy Cherringto­n hard at work reconnecti­ng the water supply to Tile City on Constant Spring Road, St Andrew, on Friday. Tile City has been experienci­ng water disruption due to the road developmen­t along Constant Spring Road over the past few months.

Newspapers in English

Newspapers from Jamaica