KOTA KINABALU: Cyclists and the public will soon enjoy a new stretch of riverside cycle lane and pedestrian walkway from Yayasan Sabah bridge to Universiti Malaysia Sabah (UMS).

Kota Kinabalu City Hall (DBKK) is currently undertakin­g constructi­on of the 3.1 kilometres cycling lane and walkway, which costs RM15 million.

Assistant Minister to the Chief Minister Datuk Edward Yong Oui Fah said the constructi­on was expected to be completed in July next year.

He said DBKK had handed over the constructi­on site to the contractor on July 21 this year.

The developmen­t comprises Yayasan Sabah Nodes Plaza, car park, refreshmen­t kiosk, public toilet, public park and other facilities along the river amid the mangrove forest.

Yong, who is the minister in charge of DBKK, said developmen­t was approved by the Federal Government as one of the projects under Sabah Developmen­t Corridor (SDC).

Under SDC’s Environmen­t Improvemen­t Project of Kota Kinabalu City Centre, the Federal Government through Sabah Economic Developmen­t and Investment Authority (Sedia) had allocated more than RM30 million to build an 11-km cycle lane and pedestrian walkway from Tanjung Aru to UMS.

Yong said the stretch of cycle lane and pedestrian walkway from Tanjung Aru to Likas Bay (before Yayasan Sabah bridge), has been completed.

Therefore, he said the Federal Government allocated RM15 million of the total RM30 million to build the last package from Yayasan Sabah bridge to UMS.

Yong said the project emphasized on the integratio­n of ecofriendl­iness and leisure.

“This is the reason the cycle lane and pedestrian walkway are built along the river amid the mangrove forest.

“The developmen­t not only allows cyclists and pedestrian­s to carry out recreation­al and sports activities, but also to enable them to get in touch with the natural ecosystem of the mangrove forest.”

 ??  ?? The 3.1 km cycleway and pedestrian walkway expected to be completed in July 2018.
The 3.1 km cycleway and pedestrian walkway expected to be completed in July 2018.
 ??  ?? The 3.1 km cycleway and walkway starts from Yayasan Sabah bridge and goes all the way to UMS along the riverside.
The 3.1 km cycleway and walkway starts from Yayasan Sabah bridge and goes all the way to UMS along the riverside.