The Borneo Post (Sabah)

MMC, Gamuda shares fall in early session

-

KUALA LUMPUR: Shares of Gamuda Bhd (Gamuda) and MMC Corp Bhd (MMC) fell in trading yesterday on the back of the government’s decision to retender unfinished undergroun­d work of the Mass Transit Line 2 (MRT2) project through an internatio­nal open tender process.

At closing, Gamuda lost 78 sen or 24.3 per cent to close at RM2.43 per share. More than 9292.1 million shares were traded. Meanwhile, MMC lost 22 sen or 16.3 per cent to close at RM1.13 per share, with more than 4.8 million shares exchanging hands.

Kenanga Research said the cancellati­on of projects would affect MMC’s earnings and as such the research firm was pessimisti­c on this news.

“We had expected more sizeable contributi­ons from the engineerin­g segment in financial year 2018-2019, with first half of 2018’s profit before tax for engineerin­g to jump 79 per cent year-on-year to RM152 million, mainly driven by MRT contributi­ons,” it said in a note today.

To-date, the group has completed 24 per cent for the elevated portion, and 33 per cent for the tunnelling portion, while this cancellati­on will affect the remaining contributi­ons from this project, with Kenanga Research estimating the annual pre-tax profit at RM70 million to RM100 million.

Meanwhile, Maybank Kim Eng Research believed that the latest developmen­t would lead to the entire MRT2 constructi­on completion to be delayed by at least half a year from its original estimation by mid-2022, due to the re-tendering exercise for the undergroun­d package.

“We think that MMC-Gamuda’s decision to walk away from the undergroun­d package is due to too significan­t a cost-down required by the government, to the extent that the risk-reward is no longer tenable.

“We are unsure if Gamuda will participat­e in the internatio­nal tender to complete the remainder of this undergroun­d package,” it added.

On Sunday, the federal government announced via the Finance Ministry that they are terminatin­g the MMC-Gamuda joint venture as the main contractor for the tunnelling works of MRT2. The joint venture was awarded the contract in 2016. For the remaining 70 per cent of the works, the government will call for an internatio­nal tender to participat­e in the project.

Additional­ly, the abovegroun­d portion of the MRT2 project is expected to be lowered by RM5.22 billion or 23 per cent of the original cost to RM17.42 billion through renegotiat­ion with MMC-Gamuda JV, the project delivery partner.

 ?? — Bernama photo ?? The latest developmen­t would lead to the entire MRT2 constructi­on completion to be delayed by at least half a year from its original estimation by mid-2022, due to the retenderin­g exercise for the undergroun­d package.
— Bernama photo The latest developmen­t would lead to the entire MRT2 constructi­on completion to be delayed by at least half a year from its original estimation by mid-2022, due to the retenderin­g exercise for the undergroun­d package.

Newspapers in English

Newspapers from Malaysia