Further delay expected for Sabah Pan Borneo – Kenanga
KUALA LUMPUR: The government's decision to take over the Pan Borneo Highway project from the existing project delivery partner (PDP) will further impact the timeline for the Sabah portion, which is already currently behind schedule.
In a note, Kenanga Research said this take-over would have a minimal impact on the existing work package contractors for the Sarawak portion as most of the work packages have already been awarded, but it could further impact Pan Borneo Sabah as some of the work packages have not yet been awarded.
The research house said development of infrastructure such as roads and ports in Sabah remains challenging as it would require much focus, attention and assistance from the relevant parties.
“The Sabah Pan Borneo has only achieved progress of 11 per cent for the 12 ongoing work packages that were awarded to local contractors.
“We foresee delays in the execution of the project underpinned by issues like land acquisition, relocation and work coordination given that it comprises 35 work packages in total,” the research house said.
Kenanga Research said the main issues causing delay to the Pan Borneo Highway project in Sabah are the land acquisition process and Environmental Impact Assessment approvals. It said out of the 12 packages already awarded to contractors, only two land acquisition packages have been cleared.
“Hence, we believe that it would be highly ambitious for Borneo Highway PDP should they aim to complete the construction works for the Sabah Pan Borneo highway by 2021, and an extension of time is inevitable if they are unable to solve the land acquisition issues,” it said. — Bernama