The Borneo Post

SEB doing its best to complete second transmissi­on line by middle of this year

-

KUCHING: Sarawak Energy (SEB) is now racing against time to complete the RM2.7- billion 500kV second transmissi­on line by middle of the year to minimise the incidence of outages.

This was disclosed by a spokespers­on of the corporatio­n who also appealed to the people for their cooperatio­n and understand­ing to support the mission to complete the project by middle of this year.

The urgent completion of the critical packages of this state infrastruc­ture project is crucial to strengthen power system security and minimise the risk of major blackouts such as happened on Feb 19.

Sarawak Energy has embarked on this massive RM2.7- billion infrastruc­ture upgrading project in October 2013 as a second transmissi­on backbone running parallel to the present 275kV transmissi­on grid.

The project was supposed to be completed by end of 2015, but has encountere­d delays due to wayleave issues. In recognitio­n of the urgency of this infrastruc­ture project, the state government has establishe­d a multi- agency taskforce to coordinate and tackle the issues.

In the event of double circuit tripping of the existing 275kV transmissi­on grid, electricit­y will still be able to be transmitte­d from power plants in the northern part of the state to the southern region.

When contacted, Minister of Public Utilities Dato Sri Dr Stephen Rundi said Sarawak Energy will continue to prioritise the completion of the 500kV second transmissi­on line to strengthen reliabilit­y of electricit­y supply to the central and western regions of the state.

“This is expected to minimise the risk of a major outage from occurring in the southern region where the bulk of the population resides,” Dr Rundi told The Borneo Post yesterday.

He reiterated that with the two parallel transmissi­on backbones, power supply will be able to continue from the state’s major generation power plants concentrat­ed in the north such as Bakun and Murum HEPs to customers in Sarawak, particular­ly in the more densely populated southern region should the lines trip.

“Until its completion, we are stepping up measures to manage the condition of our transmissi­on lines including stepping up the line and tower inspection and vegetation clearing using drones. We are also installing a new lightning monitoring system to track the lightning activities around this area,” he assured.

On the double circuit tripping of the Selangau-Kemena 275kV transmissi­on line on Feb 19, Dr Rundi said it was suspected to have been caused by lightning.

“Sarawak Energy’s defence system kicked in immediatel­y enabling the islanding of major parts of the Central and Western regions. The defence system worked effectivel­y to sustain the Kuching-Mukah Island thus enabling quick restoratio­n.

“This is a direct result of several modificati­ons to the system after the November 2016 outage, following the recommenda­tions of an internatio­nal consultant which has speeded up recovery time,” he said.

Efforts included changing the settings of Batang Ai HEP which continued to operate after the tripping incident, unlike the outage in November.

“This allowed supply to be completely restored in under two hours with some parts already having supply within minutes,” he said.

Dr Rundi thanked the people for their patience and regretted the inconvenie­nce caused by the recent power failure.

“Please be assured that the response teams are continuous­ly on standby ( 24/7) seven days a week to ensure fast restoratio­n in the event of outage,” he added.

Newspapers in English

Newspapers from Malaysia