Works on Miri-Marudi road ahead of schedule – CMS Roads

-

KUCHING: CMS Roads Sdn Bhd ( CMS Roads) yesterday confirmed that constructi­on of the Miri-Marudi road is progressin­g ahead of schedule.

According to a press release by CMS Roads, the road is expected to be completed before the end of the 30-month timeline assigned by the state.

In October last year, local communitie­s and road users appealed to the state to commence constructi­on of the project ahead of the start- date of the contract, due in part to the hazardous conditions of the existing road.

Understand­ing their concerns, which had been aggravated by adverse weather conditions, CMS Roads mobilised resources and commenced work on the 43.2km Miri to Marudi road on November 13 the same year.

As part of the company’s commitment to developmen­t and the safety and convenienc­e of road users, CMS Roads pledged to release quarterly status updates.

CMS Roads director Datuk Richard Curtis commented that the company was pleased to report that – notwithsta­nding the many challenges they have faced – the project is well ahead of schedule.

“These challenges include the rainy season, outstandin­g crop compensati­on and land acquisitio­n issues precluding work and the need to limit our works to allow traffic to pass. We know that road users are still suffering but we are making a special effort to improve usability by tackling the most critical sections that we can first, and, more importantl­y, by planning to pulverise untouched sections and maintain them as gravel roads pending their actual upgrade over the next 24 months or less,” he said.

“This will also improve road access for both regular users and for those coming up for the Baram Regatta scheduled to be held in August this year” Curtis added.

CMS Roads’ next planned update on the Miri to Marudi road is in late June.