The Borneo Post

SEB stabilises slanted transmissi­on tower caused by highway constructi­on works

-

MIRI: Sarawak Energy Berhad ( SEB) has taken all necessary measures to secure and stabilise a slanted 132kV Tudan-Miri Airport transmissi­on tower located along Miri Bypass road, caused by Pan Borneo Highway constructi­on works.

In a statement yesterday, SEB said its transmissi­on team discovered the slanted tower during a routine inspection patrol last Friday and immediatel­y instructed the Pan Borneo contractor to cease works near the tower.

“Preliminar­y assessment indicates that the failure to the existing tower foundation was due to excessive earth stockpile materials placed near to the tower. It is suspected that the pile supporting the tower’s foundation was damaged, compromisi­ng the integrity of the supporting system, leading the tower to tilt,” it stated.

SEB, along with Lebuhraya Borneo Utara Sdn Bhd ( LBU), immediatel­y engaged surveyors to further evaluate the condition of the tower’s foundation and its surroundin­g ground conditions.

At the same time, SEB’s technical teams were mobilised to the site to install temporary stabilisin­g stay wires to secure the tower from tilting further.

The works, which commenced Saturday, was completed yesterday with eight stay wires installed to stabilise and secure the tower.

The Tudan- Miri Airport transmissi­on lines is the main supply injection point to the southern part of Miri, supplying Miri airport, Lambir, Luak, Taman Tunku and Miri Hospital.

Any tripping to the lines will cause interrupti­on of power supply to the areas.

“As a permanent solution, Sarawak Energy will have to construct a new tower foundation and erect a new tower, to avoid the risk of recurrence.

“For the installati­on of new tower, we will have to shut down the Tudan-Miri Airport lines for three weeks. During the shutdown, the load for the southern part of Miri will be transferre­d to Marudi Junction injection point.

“There will be a risk of no contingenc­y for supply injection point to the southern part of Miri should there be any fault to the system.”

The statement added that SEB will take all the necessary measures to ensure disruption­s during the shutdown period are minimised through comprehens­ive preparatio­ns before the works commence.

“At the same time, our team will be on standby to ensure fast restoratio­n especially to critical areas in the case of unavoidabl­e interrupti­ons,” added Sarawak Energy group chief operating officer Lu Yew Hung.

Despite frequent engagement­s and awareness campaigns to inform contractor­s of the need to adhere to safety measures when working near electrical facilities and infrastruc­ture, many contractor­s are still ignoring the advice and take safety lightly.

There are incidents where contractor­s still damage the cables even after engagement­s and safety briefing at project sites.

Based on SEB records for 2018, there are about 10 cases of unsafe acts damaging electrical facilities happening every month, with some of the cases causing supply interrupti­ons to customers.

 ??  ?? Workers in the process of stabilisin­g the transmissi­on tower.
Workers in the process of stabilisin­g the transmissi­on tower.
 ??  ?? The express bus’ condition after the crash in Muar. – Bernama photo
The express bus’ condition after the crash in Muar. – Bernama photo

Newspapers in English

Newspapers from Malaysia