LMT 2 to start operating in 2026

-

LUMUT: A total of RM282 million has been allocated for the Lumut Maritime Terminal 2 (LMT 2) constructi­on project in Batu Undan, Segari near here, which is expected to be fully operationa­l by early 2026.

Perak Menteri Besar Datuk Seri Saarani Mohamad said the LMT 2 will be developed in three phases on a 90-hectare site, adding that it is one of the components of the 10-year Lumut Port Strategic Business Plan.

“The first phase involves land acquisitio­n and site preparatio­n works, while the second phase focuses on dredging and the constructi­on of onshore and marine infrastruc­ture.

“The third phase will concentrat­e on the terminal developmen­t with appropriat­e handling facilities and equipment, and the total cost of the developmen­t will be borne by Lumut Port,” he told the media after officiatin­g the groundbrea­king ceremony for LMT 2 yesterday.

Also present were State Secretary Datuk Ahmad Suaidi Abdul Rahim and LMT chairman Datuk Azian Osman.

Saarani said the main objective of the constructi­on of LMT 2 is to make Lumut Port the most efficient cargo terminal operator in Southeast Asia, in line with the Lumut Maritime Industrial City (LUMIC) initiative, which aims to drive the state’s economic growth.

“The key pillars of the project include increasing capacity and operationa­l efficiency, developing infrastruc­ture in line with industry developmen­ts, and providing modern and safe facilities.

“At the same time, the constructi­on of LMT 2 also emphasises environmen­tal quality preservati­on, in line with the state government’s efforts to ensure the management of mineral resources and natural resources is according to establishe­d standards,” he said.

He added that the LMT 2 is expected to create 200 jobs in the maritime industry.