The Star Malaysia

Saving RM5bil on MRT2

Retender of transit rail project works will save us RM5bil, says Lim

- By YIMIE YONG yimie.yong@thestar.com.my

MMC-Gamuda JV’s Mass Rapid Transit 2’s undergroun­d contract has been terminated. And a retender of all unfinished works is being called. In so doing, the government not only saves 23% from the original RM22.64bil, rail passengers can enjoy cheaper trips when it is up and running.

PETALING JAYA:

The government and the principal player in the constructi­on of the second phase of the Klang Valley Mass Rapid Transit (MRT2) project has come to new terms of agreement to complete the infrastruc­ture project.

Under the new terms, MMC Gamuda Joint Venture (MMCGamuda), which was given the mandate to see through the public transporta­tion job in February 2014 at a cost of RM28bil, would see through the completion of the above- the- ground portion at RM17.42bil.

Under the original terms, MMCGamuda was appointed as the Project Delivery Partner (PDP).

Under the PDP concept, MMCGamuda was to complete the job within time and cost.

The project owner and funder is MRTCorp Sdn Bhd, an entity owned by the government.

Under the new terms, MMCGamuda would complete the abovegroun­d works at RM17.42bil as a turnkey contractor.

This effectivel­y means that MMCGamuda has to ensure completion of the project within the specified cost and hand it to the government on time.

Another major difference in the new MRT2 contract is that the government has decided on an open tender for the undergroun­d works.

According to a statement by the Finance Ministry, the Cabinet decided to terminate MMC-Gamuda’s undergroun­d contract on the MRT2 and retender all unfinished undergroun­d work through an internatio­nal open tender.

This came after both the federal government and MMC-Gamuda failed to reach an agreement relating to the undergroun­d portion of the project.

Minister Lim Guan Eng said that with the decision, the federal government could achieve significan­t savings by retenderin­g the undergroun­d work compared to the offer made by the existing contractor.

He also said the government would be able to garner RM5.22bil or 23% in savings through a reduction in cost and rationalis­ation in work scope without cancelling any of the above-ground stations.

This came about after the Cabinet accepted an offer made by MMCGamuda on Oct 3, through their letters dated Aug 15 and Sept 7, to complete the above-ground portion of the MRT2 project as a turnkey contractor for RM17.42bil versus the original RM22.64bil.

“There is already a RM5.22bil or 23% saving made from the abovegroun­d portion of the MRT2 project.

“More savings will be gained when the undergroun­d portion is retendered soon.

“Furthermor­e, the expected cost reduction will cut the fares passengers have to pay and boost public transport usage in the Klang Valley,” he said.

The Finance Ministry had embarked on a cost rationalis­ation exercise on the MRT 2 since May, with the cooperatio­n of the Attorney General’s Chamber, Transport Ministry, Mass Rapid Transit Corporatio­n Sdn Bhd (MRTCo) and the private sector.

An engineerin­g consultanc­y firm was engaged to conduct the cost rationalis­ation.

The MRT2 project was approved by the Cabinet on Feb 26, 2014 with an initial estimated cost of RM28bil.

However, Lim said the figure did not include consultant fees, PDP fees, interest costs and the overhead cost for MRTCo.

The Cabinet also agreed to the appointmen­t of MMC-Gamuda Joint Venture as the PDP to manage and complete the project.

Lim noted that the MRT2 cost increased to RM56.93bil due to the approval for a Railway Scheme that had a new line extended to Bandar Malaysia, a change in scope, depreciati­on of the ringgit and various other factors.

The overall cost comprised RM39.35bil constructi­on cost, RM6.18bil land acquisitio­n cost, RM0.36 bil for feeder buses and depot costs, RM1.2bil of other costs as well as RM9.84bil worth of interest expenses during constructi­on.

The MRT2 and Light Rail Transit phase 3 (LTT3) projects came under review following the change in government on May 9.

The phase 3 of MRT and the High Speed Rail projects were deferred.

The project owner for LRT3 is Prasarana that has seen changes at the top after the Finance Ministry revealed that the cost of the project rose to RM31bil from its initial RM10bil.

The LRT 3 project is now to be completed at RM16.6bil.

As for MRT2, this is the first time the government has come up with a detailed review on the cost of the project.

The MRT2 line runs from Sungai Buloh to Serdang and ends in Putrajaya. It is to complement the existing MRT1 line that runs from Sungai Buloh to Kajang.

 ??  ??
 ??  ?? Getting back on track: According to Lim, the MRT2 undergroun­d project’s retender via internatio­nal open tender promises a 23% reduction in costs while sparing stations above ground.
Getting back on track: According to Lim, the MRT2 undergroun­d project’s retender via internatio­nal open tender promises a 23% reduction in costs while sparing stations above ground.

Newspapers in English

Newspapers from Malaysia