The Star Malaysia

Govt sets 2023 forMRT2tob­e up and running

Sungai Buloh-Serdang-Putrajaya project must stay within rM30.53bil, says Lim

- By MAZWIN NIK ANIS mazwin@thestar.com.my

The government wants the Sungai Buloh-Serdang-Putrajaya (MRT2 or SSP Line) project to be on time so that it will be operationa­l by 2023, while remaining within the revised cost of RM30.53bil, says Finance Minister Lim Guan Eng.

He said following a cost-cutting exercise, the government has managed to shave RM8.82bil or 22.4% of the original constructi­on cost of the line, which was RM39.35bil.

The cuts came from the conversion of the project structure from a project delivery partner model to that of a turnkey model, thus creating savings in the project delivery partner (PDP) fee.

Other savings came from cuts to the allocation of reimbursab­les, contingenc­ies and provisiona­l sums.

Savings were also achieved by slowing down constructi­on work and downscalin­g of certain specificat­ions of the project, an approach Lim described as “progressiv­e”.

“This avoids building the line as quickly as possible to its maximum capacity, but without compromisi­ng on quality, safety and operationa­l efficiency of the system,” he said, adding that one such example is the deferred opening of the Bandar Malaysia North and Bandar Malaysia South undergroun­d stations.

There were also outright downsizing of specificat­ions and scope of work of electrical and mechanical systems, as well as on the amount of equipment.

For example, the number of train sets for the SSP Line has been reduced from 58 to 49 while all the stations will sport simpler architectu­ral finishes.

“The savings will enable us to do more infrastruc­ture work in the future,” he said after witnessing the signing of a supplement­al agreement between the project delivery partner for MRT2, MMC Gamuda KVMRT (PDP SSP) Sdn Bhd, and project owner, Mass Rapid Transit Corporatio­n Sdn Bhd (MRT Corp)

Also present were Transport Minister Anthony Loke, MRT Corp chief executive officer Abdul Yazid Kassim and MMC Gamuda directors Datuk Seri Che Khalib Mohamad Noh and Datuk Paul Ha.

The 52.2km SSP Line began constructi­on in 2016, and it is the second MRT line after the Sungai Buloh-Kajang Line.

Asked if the revival of the Bandar Malaysia transport terminal project would see the MRT stations there be opened earlier, Lim said this would be evaluated after looking at the overall progress of the project.

“If we do it (open the station) too fast without having the volume and capacity, that will be a loss. We have to factor in demand before deciding on this,” he said.

The SSP Line is now 70% complete, with major works expected to be completed in 2022 and the line to be operationa­l by January 2023.

Phase one of the SSP should run from the Kwasa Damansara station to the Kampung Batu station by July 2021, while phase two (of full opening) will see trains running all the way to the Putrajaya Sentral station by January 2023.

On the e-Tunai Rakyat programme, Lim refuted claims that it was an attempt by the government to obtain personal informatio­n, pointing out that there was no need to go through such lengths as personal informatio­n could be obtained from one’s identity card.

“I don’t see how this can be construed as an effort to get personal informatio­n. If there is any benefit from this exercise, it is so that we know something about consumptio­n patterns.

“But the government doesn’t even need the informatio­n because we are not involved in business or trading. It is just us wanting to do something for the people,” he said of the programme introduced under Budget 2020 to encourage the use of cashless payments.

Newspapers in English

Newspapers from Malaysia