The Sun (Malaysia)

DUKE 2 91% complete

> Expressway will benefit city dwellers by reducing travelling time

-

KUALA LUMPUR: Phase two of the Duta-Ulu Klang Expressway (DUKE) connecting the east and west of the capital city via a 16km link is currently 91% complete.

Konsortium Lebuhraya UtaraTimur (KL) Sdn Bhd (Kesturi) director Zakaria Shaffie said with another 9% to go, the longawaite­d expressway would be completed by year-end, and would be fully operationa­l by early next year.

“The remaining works comprise the constructi­on of the elevated structure for the expressway,” he told reporters during a technical visit to the project site with participan­ts of the 2nd Internatio­nal Road Federation (IRF) Regional Asia Congress and Exhibition 2016, here, yesterday.

“DUKE 2 will surely benefit city dwellers, especially Segambut and Sungai Buloh residents, and we believe that with the expressway we can reduce traffic on local roads by 20%,” he said.

Constructi­on of the RM1.18 billion DUKE Phase 2 project began in December 2013 and it comprises two additional links, namely Tun Razak Link (TR link) and Sri Damansara Link (SD Link), which will be connected to the existing DUKE 1.

The 7km SD Link begins at the Menjalara Interchang­e at Bandar Menjalara and ends at the Segambut Interchang­e in Jalan Segambut and is expected to reduce travelling time to 12 minutes.

The 9km TR Link is from Jalan Tun Razak near Kuala Lumpur Hospital to the Sentul Pasar Interchang­e in Jalan Gombak.

Zakaria said the DUKE 2 project will also involve constructi­on of the park-andride facility in Segambut.