Malta Independent

Constructi­on of two new lanes and footpath on tal-Balal road ‘nearing completion’

● Weather issues, weak existing foundation­s among reasons for tal-Balal project delays

- ■ Kevin Schembri Orland

The constructi­on of the two new lanes and the new footpath on tal-Balal road is nearing completion, Infrastruc­ture Malta told The Malta Independen­t.

Infrastruc­ture Malta has given its reasons for the delays in the completion of the tal-Balal road linking San Gwann and Naxxar in response to questions posed by this newsroom.

Last November, Infrastruc­ture Malta said that efforts were being made to achieve completion of works possibly by the end of 2018. This did not happen and works are still underway.

This newsroom has asked Infrastruc­ture Malta for the exact original completion deadline for the road project, when it is now expected that the project would be completed and what the reasons for the delays were. While the representa­tive highlighte­d that works are nearing completion, no exact date was given.

The agency’s representa­tive explained through an email, as well as a subsequent phone call, that bad weather hampered progress over the past months.

Another major obstacle, the representa­tive said, was that the road was originally built over infilled disused quarries.

“Whilst rebuilding the road, the contractor­s are also carrying out extensive works to reinforce the existing carriagewa­y’s weak foundation­s. This road link was originally built over a number of disused quarries, which had been infilled with debris and other materials. These inadequate foundation layers were causing sections of the asphalt surface to cave in, increasing safety risks to road users. This infill material was excavated as part of this project and replaced with deep undergroun­d foundation structures built with large stone blocks and concrete.”

A number of other reasons were also provided by the agency, such as the laying of cables and other infrastruc­ture and the implementa­tion of the second phase of the project at the same time as the first to avoid works later on.

Infrastruc­ture Malta is upgrading Triq tal-Balal, a major road link between Naxxar, Gharghur, Iklin and San Gwann, to add two new lanes, new footways, safer bus lay bys, pedestrian crossing facilities and cycling-friendly infrastruc­ture.

This investment was planned to be developed in two phases, the agency said.

“The ongoing works were scheduled to include the first phase only, to widen the road to three lanes, two southbound, from Naxxar to San Gwann, and a single lane in the opposite direction. Following initial works, most of Triq tal-Balal has been available to road users as a threelane road for months.

“The agency allocated additional resources to implement the second stage of the project as well, including the introducti­on of a second lane in the northbound direction. Infrastruc­ture Malta also included a new footway along the entire 1.8 kilometre route, to facilitate pedestrian access between Naxxar and San Gwann. The pre-existing road layout did not include any pedestrian infrastruc­ture.

“All works are being carried out whilst keeping the road open in both directions at all times during the day. Over 2,100 road users travel through this road every hour during the morning and afternoon peaks. Additional measures are also being taken to minimise disruption­s to the industrial and commercial operations in this area.”

The constructi­on of the two new lanes and the new footpath is nearing completion, the agency said.

“Sections of them are already being used by road users instead of the two pre-existing lanes, which are currently being reconstruc­ted. The project also includes over two kilometres of new rubble walls, replacing the existing dilapidate­d boundary walls, the constructi­on of a safer central strip with vehicle restraint systems and several other structures.”

To reduce the risks of digging up the new road surface after it is completed, Infrastruc­ture Malta is collaborat­ing with the utilities and with telecommun­ication services providers to upgrade existing undergroun­d distributi­on networks along the same road, the agency added.

“The new pipelines replaced old water mains dating back decades. The new undergroun­d cables will be used instead of a stretch of high voltage aerial lines on poles supplying electricit­y to the rural areas between San Gwann and Birkirkara. The old poles and aerial lines can be dismantled after the new undergroun­d connection is energised. Another four-kilometre network of ducts and cables was installed along the same road to energise a new LED street lighting system comprising 160 lamp posts.

“Weather permitting, the two phases of this project are planned to be completed as soon as possible.”

Through the ongoing upgrade, road users travelling along Triqtal-Balal and its roundabout­s will experience travel time reductions ranging from 30 to 40 percent less than current durations, the agency said in its replies. “These figures are based on the existing road capacity, ongoing traffic count analysis for this road and other nearby junctions and connection­s as well as future demand projection­s. The indicated improvemen­ts will also lead to a decrease in vehicle emissions caused by long queuing times.”

This €4 million infrastruc­tural investment also includes the rebuilding of Triq tal-Balal’s four roundabout­s to introduce new bypass lanes and improved junction designs, the agency said.

 ??  ??

Newspapers in English

Newspapers from Malta