Malta Independent

Virus outbreak among workers developed ‘at a critical point in the project’

- KEVIN SCHEMBRI ORLAND

The news that a number of Marsa Junction Project workers tested positive for COVID-19 came ‘at a critical point’ in the project’s implementa­tion, days before three flyovers were meant to open, a spokespers­on for Infrastruc­ture Malta told The Malta Independen­t.

The spokespers­on, responding to questions by this newsroom, confirmed that works on the project stopped after 8 September, when the agency issued a statement that 21 people working on the project tested positive. The spokespers­on stressed that the agency provided all the required informatio­n to the health authoritie­s and supported the project contractor to take additional measures to protect its personnel.

“All workers who could have been in contact with the ones who tested positive for the virus were asked to self-isolate and encouraged to seek further advice from the government’s COVID-19 support services, as necessary. All works on site were stopped, as recommende­d by the health authoritie­s,” the spokespers­on said.

The agency said that these measures helped to ensure that the spread of the virus was contained. “While the 21 workers who contracted the virus last week selfisolat­ed and started receiving the required treatment, subsequent testing of other project workers, who are also in self-isolation, resulted negative. The workers will be retested in the coming days, so that the health authoritie­s can confirm whether they can resume works on site next week.”

“Unfortunat­ely, this situation developed at a critical point in the implementa­tion of the Marsa junction project, days before Infrastruc­ture Malta was planning to open another three of this investment’s seven flyovers. As soon

as the health authoritie­s confirm that works on site can resume, the contractor will need up to 15 days to open the new flyovers, weather permitting.”

The agency’s projects implementa­tion team is reviewing and reorganisi­ng this phase of the project, the spokespers­on said, “to ensure that when the contractor’s workers return on site, they carry out the last works on these three flyovers in the shortest time possible, to limit the impact of this delay as much as possible.” The agency was also asked whether, given the start of the rainy season, more delays can be expected not only on the Marsa junction project, but also on other roadwork projects around the island.

The agency said that while rainfall can lead to the postponeme­nt or reorganisa­tion of certain stages of the Marsa Junction Project and other road works by a few days, especially when laying road foundation­s and overlying asphalt surfaces, “such situations are normally foreseeabl­e and factored in project timelines in advance, so that they do not have significan­t impacts on deadlines.”

The new flyover structures that will be opened in the coming weeks include uninterrup­ted, southbound connection­s from Aldo Moro Road, Marsa, to Giuseppe Garibaldi Road, Luqa, and to Santa Luċija Avenue, towards Santa Luċija and Tal-Barrani Road, Tarxien, the spokespers­on said. “The Santa Luċija Avenue’s southbound carriagewa­y, which was closed a few months ago, will once again be available to road users.” The spokespers­on explained that they are working to remove the bottleneck of the existing diversion lanes between Aldo Moro Road and Garibaldi Road, facilitati­ng journeys to Luqa, Gudja, the Airport and the Kirkop Tunnels.

“The three flyover structures completed last year, which are temporaril­y being used in contraflow in the same direction as the three new ones, will subsequent­ly be closed for a few weeks for final asphalt laying and for the installati­on of expansion joints, so that they can be reopened in the northbound direction.”

The spokespers­on said that when the northbound flyovers are reopened, Infrastruc­ture Malta will also open the seventh flyover structure, which was completed last month. It will link the northbound carriagewa­y of Santa Luċija Avenue, currently closed, to the Addolorata Cemetery, to a new park and ride area forming part of the same project and to Il-Gvern Lokali Road, towards Qormi (Turkish Cemetery area).”

The spokespers­on said that the Santa Luċija Avenue was closed earlier this year due to the constructi­on of the new Santa Luċija Roundabout Underpass. “Infrastruc­ture Malta will reopen this road’s newly-rebuilt southbound carriagewa­y along with the three new Marsa flyovers in the coming weeks. It is planning to reopen the northbound carriagewa­y, also rebuilt as part of the same two projects, a few weeks later.”

Beneath the flyovers, Infrastruc­ture Malta is building other new roads that will form part of the same multi-level intersecti­on, including northbound and southbound lanes between Sir Paul Boffa Avenue’s northbound carriagewa­y and Aldo Moro Road, the spokespers­on added. “The project will also include lanes leading to two new park and ride areas, to the Addolorata Cemetery, to nearby industrial zones and to other areas.”

The spokespers­on added that Infrastruc­ture Malta is building two undergroun­d reservoirs to harvest 1.5 million litres of rainwater for the irrigation of new green areas. Stormwater pipelines will also be constructe­d.

The Marsa Junction Project is cofinanced through the European Union’s Cohesion Fund and the Connecting Europe Facility.

 ??  ??

Newspapers in English

Newspapers from Malta