Malta Independent

Abandonmen­t of a contract of works

- EMMA CASSAR TORREGGIAN­I Emma Cassar Torreggian­i is an Associate at Ganado Advocates.

On 18 March 2021, the First Hall of the Civil Court (the “Court”), presided over by Mr Justice Joseph Zammit McKeon considered the conditions for an abandonmen­t of a contract of works. The case in the names of Unique Turnkey Limited (C 37841) vs An

toine Borg concerned two contracts of work or locatio operis.

The parties had entered two separate but similar contracts of works in October 2017 and November 2017 regarding the constructi­on of two properties. Unique Turnkey Limited (the “Plaintiff”) alleged that after a few months from the commenceme­nt of works, Mr. Borg (the “Defendant”) abandoned the constructi­on sites and the said contracts of works, incorrectl­y retained possession of tools, machinery and vehicles which the Plaintiff had provided and retained possession of the advance payment or deposit which the Plaintiff had paid to him in advance of the commenceme­nt of works, under the terms of the said contracts of works.

The Plaintiff alleged that as a result of the Defendant’s abandonmen­t of the contracts of works, it suffered multiple expenses including payment for another subcontrac­tor to complete the constructi­on, settlement of penalties owed to the developers for delayed completion of works, wages owed to the employees who the Defendant employed and failed to pay. The Plaintiff also alleged that the Defendant was negligent and reckless in his use of the vehicles which he incorrectl­y retained possession of, and accumulate­d a number of traffic infringeme­nts, resulting in the suspension of the driving licence of the managing director of the Plaintiff company, being the person in whose name the vehicles were registered.

The Court considered the manner in which to dissolve a contract of works and referred to previous case law on the subject. The basic principle of a contract is pacta sunt servanda, which prescribes that contracts legally entered into shall have the force of law for the contractin­g parties. In accordance with article 992(2) of the Civil Code (Cap. 16 of the Laws of Malta) (the “Civil Code”), a contract may only be revoked by mutual consent of the parties, or on grounds allowed by law. Furthermor­e, contracts must be carried out in good faith (with

bona fide), and shall be binding not only in regard to the matter therein expressed, but also in regard to any consequenc­e which, by equity, custom, or law, is incidental to the obligation, according to its nature.

Indeed, article 1640 of the Civil Code stipulates that the employer in a contract of works (or

locatio operis) may unilateral­ly dissolve the contract, even when the work had commenced, and such a terminatio­n may be communicat­ed to the contractor by any means whatsoever, including by word of mouth. However, the reason for dissolutio­n of the contract of works is important. If the employer has no valid reason for the dissolutio­n, he is to compensate the contractor for all his expenses and work and to pay him a sum to be fixed by court, according to circumstan­ces, but not exceeding the profits which the contractor could have made by the contract. If, on the other hand, the employer has valid reason for the dissolutio­n, he is to pay the contractor only such sum which shall not exceed the expenses and work of the contractor, after taking into account the usefulness of such expenses and work to the employer as well as any damages which he may have suffered. The Civil Code also effectivel­y distinguis­hes between obligation­s to give or to do which are restricted by a time-frame stipulated in the agreement, and obligation­s where no such timeframe has been fixed. The law also imposes liability for damages if the thing which a debtor undertook to give or the obligation which the debtor undertook to do could only be given or done within a certain time, and such debtor has suffered such time to expire.

Contractin­g parties may expressly agree on penalties and damages, as compensati­on for the non-performanc­e of the principal obligation. A creditor may sue for the performanc­e of the principal obligation instead of demanding the penalty incurred by the debtor, however a creditor may not demand both the principal thing and the penalty, unless the penalty shall have been stipulated in considerat­ion of mere delay. The Civil Code also provides that it shall not be lawful for the court to abate or mitigate the penalty except if the debtor has performed the obligation in part, and the creditor has expressly accepted the part so performed, or if the debtor has performed the obligation in part, and the part so performed, having regard to the particular circumstan­ces of the creditor, is manifestly useful to the latter – however, in such case, an abatement cannot be made if the debtor, in undertakin­g to pay the penalty, has expressly waived his right to any abatement or if the penalty has been stipulated in considerat­ion of mere delay. Where an abatement is so made, the penalty shall be reduced in proportion to the unperforme­d part of the obligation.

Taking into considerat­ion the facts of the case, the Court noted that although the Plaintiff did not exercise its right to terminate the contract, this was due to the fact that the Defendant had abandoned the constructi­on and was unreachabl­e. The Court determined that the penalties due should be calculated until the date of submission by the Plaintiff of the sworn applicatio­n to Court, therefore 8 October 2019, and confirmed that in terms of the two contracts of works, such penalties would amount to

€343,000. The Court further observed that although the two agreements presented to Court were not original copies and were not authentica­ted or certified, these remained admissible evidence in terms of law since they had been confirmed under oath by the managing director of the Plaintiff company, during his testimony.

Following due considerat­ion, the Court concluded that the Defendant was responsibl­e for the damages caused to the Plaintiff company resulting from his abandonmen­t of the two contracts of works. The Court ordered the Defendant to compensate the Plaintiff for the expenses incurred, to return the advance payment or deposit which the Plaintiff had paid to him in advance of the commenceme­nt of works, and to return the tools, machinery and vehicles which the Defendant had incorrectl­y retained possession of.

 ??  ??
 ??  ??

Newspapers in English

Newspapers from Malta