Malta Independent

SVP €274M CONTRACT

Falzon ‘convinced’ internal scrutiny will be carried out

-

Social solidarity Minister Michael Falzon said today he is convinced that “internal scrutiny” will be carried out into a highly irregular €274 million Saint Vincent de Paul contract.

The contract was given to a consortium formed by James Caterers Ltd and a subsidiary of the db Group in 2017, for the provision and servicing of 500 beds at the elderly care home.

The Auditor General has expressed doubt on whether the contract “secured value for money” and also found that no political authorisat­ion to enter into a negotiated procedure with the consortium was requested from and provided by the Parliament­ary Secretarie­s involved.

Falzon was responsibl­e for the elderly sector until last year’s reshuffle, when care homes were transferre­d under the responsibi­lity of Michael Farrugia. Both ministers have passed the buck when asked who will be shoulderin­g the political responsibi­lity.

Quizzed by journalist­s on Thursday, Falzon said, “the report is what it is. Like any other report it will be scrutinise­d internally.”

Falzon said he had not had “the luxury of analysing the report” before it was tabled in Parliament on Wednesday but said “the government will take any steps that are deemed necessary.”

Asked if the contract will be cancelled, Falzon said this was not his decision to make. The sector no longer falls under his portfolio and he was not involved in the entire process, he continued.

He said that that the project was very much needed since it had effectivel­y doubled the bed space at Saint Vincent de Paul.

“Without it, the elderly situation would have exploded. I understand that the wellbeing of the elderly might not be the NAO’s main concern. This is an innovative concept, and we will see how it works. But I am convinced that an internal scrutiny will be carried out.”

Asked who will shoulder political responsibi­lity, he said he can only speak on his own behalf.

“There was no political interferen­ce on my part. The report makes it clear that the mechanism that should have been used by the government was in fact used and there was no political interferen­ce.”

Asked to explain the fact that the deal never went up before the Cabinet, Falzon said he cannot answer on issues he was not involved in.

He insisted he is no longer responsibl­e for the sector. Pressed on the matter, Falzon said: “as journalist­s who have access to the NAO report from beforehand, how is possible that you do not know who is responsibl­e for a sector?” The National Audit Office has expressed doubt on whether a €247 million tender awarded to a consortium to manage four blocks at Saint Vincent de Paul secured value for money.

The NAO also found that no political authorisat­ion to enter into a negotiated procedure with the consortium was requested from and provided by the Parliament­ary Secretarie­s involved.

The report, tabled in Parliament on Wednesday, looked into the tender awarded in 2017 to the JCL (James Caterers Limited) and MHC (Malta Healthcare Company, a subsidiary of db Group) Consortium for a 500bed extension at the Luqa nursing home. The contract was awarded following a negotiated procedure.

The constructi­on of these blocks was linked to an additional investment valued at €29 million that the consortium was to provide, at no cost to SVP, in relation to a separate tender for comprehens­ive services, that also comprised the provision of catering and the constructi­on of a kitchen. The contract relating to the tender, also entered into on 14 November 2017, was valued at €57,000,000.

‘Fallacious’ concept

In its report, the NAO said it noted irregulari­ties in its review of this procuremen­t process, most serious of which are those relating to the concept of an additional investment, the legal basis of the negotiated procedure, the absence of authorisat­ion and concerns on failure to secure value for money.

“The NAO was unable to determine how the additional investment component originated, notwithsta­nding that this was an innovative requiremen­t of the call for tenders for comprehens­ive services. This Office has reservatio­ns as to why no parameters that were to guide potential tenderers formulate the additional investment were set. This concern assumes greater relevance given the disproport­ionate weighting that this was assigned in the evaluation criteria.”

“The concept of an additional investment at no cost to the contractin­g authority, as applied in this case, is fallacious, for in a transactio­n of significan­t value with commercial interests, nothing is ever secured for free,” the NAO said.

“Bidders could recover the additional investment by factoring this cost into the pricing for the provision of meals or through other related agreements.”

‘Urgency’ claim not justified

The office also said that the basis cited as justificat­ion authorisin­g the negotiated procedure was in breach of legislativ­e provisions, “thereby possibly leading to the invalidity of the procuremen­t undertaken.”

Authorisat­ion was sought by the SVP, endorsed by the Ministry for the Family and Social Solidarity (MFSS) and granted by the Department of Contracts (DoC) on the basis that competitio­n was absent for technical reasons and for reasons of extreme urgency.

But the NAO said there existed no technical reasons that precluded competitio­n since the management of these blocks could have been undertaken by other operators.

“Notwithsta­nding reference to urgency, this was not justified as the blocks were to be under constructi­on for at least 18 months, during which the SVP could procure these services through an open procedure.”

No political authorisat­ion

Conspicuou­sly absent was any political authorisat­ion endorsing Government’s commitment to a project of over €274,000,000 and entered into directly with the JCL and MHC Consortium.

The agreement for the management of the additional blocks was not brought to the attention of Cabinet despite its materialit­y and the project’s national importance.

The NAO concluded that no political authorisat­ion to enter into a negotiated procedure with the Consortium was requested from and provided by the Parliament­ary Secretarie­s involved.

“Considerin­g the extent of the project, its materialit­y, its significan­ce due to the increase in capacity of existing facilities, and that negotiatio­ns had been underway for several months, the NAO deems incredulou­s how this project did not draw the attention of the Parliament­ary Secretarie­s responsibl­e for the SVP.”

Even if the project was not referred to the Parliament­ary Secretarie­s for their authorisat­ion, their failure to enquire as to the regularity of this procuremen­t is in clear breach of their duty arising from the political post held, it said.

Value for money?

Of concern to the NAO is that the MFSS, the SVP and the DoC pursued the offer by the JCL and MHC Consortium and assigned it the management of the new blocks without adequate considerat­ion.

The Consortium offered a discount on costs incurred by the SVP determined through an independen­t analysis.

“This Office maintains that this should have been determined prior to any decisions made, rather than when the decision to assign the management to the Consortium had been taken. No analysis as to what Government was charged for highly dependent residents in other care homes was undertaken. The rate charged by these homes was significan­tly lower than that of the Consortium, €99.17 daily per resident per occupied bed. The average daily rate that Government was paying private contractor­s for persons with a high dependency in 2016 was €51.06. In November 2020, that is, by the handover of the blocks, the rate charged by the Consortium was revised to €118.44, as against the average of €65.13 charged under the Buying of Beds Scheme. This difference raises doubt whether value for money was secured.”

 ??  ??
 ??  ??

Newspapers in English

Newspapers from Malta