The Malta Independent on Sunday

Commission­ing of power station on time would have cost the country € 138 million

-

If the new Delimara power station had been commission­ed in 2015 as per the Labour Party’s electoral pledge, it would have cost the country an extra €138 million over the last two years, according to an independen­t analysis commission­ed by the Nationalis­t Party seen by this newspaper.

The study estimates the addi- tional costs the country would have incurred in 2015 and 2016 if the country’s energy requiremen­ts had been met by the new Electrogas power plant instead of the electricit­y interconne­ctor.

In actual fact, the study finds it was the use of the interconne­ctor, which was commission­ed in March 2015, which had been responsibl­e for keeping the prices of electricit­y down over the last two years.

According to the study, if the Electrogas power station had been up and running as originally planned as per the government’s electoral programme, and had begun to supply the same energy purchased from the interconne­ctor, it would have cost the country €54 million more in 2015.

Using the same yardstick for 2016, when over 70 per cent of the country’s energy needs were purchased from the interconne­ctor, the Electrogas power station would have cost the country €84 million more in 2016.

Moreover, the expert analysis also calls into question the actual need for a new power station in the first place, given that energy production data for 2016 shows that the interconne­ctor is able to cope with three-quarters of the country’s energy needs and that the BWSC plant would have been more than enough to cater for the remainder of the country’s energy requiremen­ts.

According to the analysis, the additional cost of producing energy locally, as opposed to sourcing it from the interconne­ctor, is in the region of €138 million, almost €70 million a year, over 2015 and 2016 together.

2015

According to data from the National Statistics Office, during 2015 Malta bought electricit­y from the interconne­ctor amounting to a grand total of 1,053,981 Mwh, since the project was commission­ed in March 2015.

The workings estimate the extra production costs Malta would have incurred if the equivalent amount of energy imported from the interconne­ctor in 2015 had been produced by Electrogas.

Employing the total 2015 energy volume of 1,053,981,000 kWh, the additional cost of producing the same volume by Electrogas would have been (x €0.051 per kWh), or €54 million. • Electrogas rate €0.096 per Kwh • Interconne­ctor rate €0.03c – €0.06c per Kwh (the study uses an average price of €0.045c per kwh) • The difference in rates is of €0.051 per Kwh

2016

Figures from Eurostat, the European Union’s statistica­l arm, show that 72 per cent of Malta’s energy requiremen­ts over the course of 2016 (January through August 2016) were imported from the interconne­ctor. This was the case this year because the BWSC plant was switched off so that the conversion to natural gas to take place.

The figures clearly show that the interconne­ctor on its own is able to satisfy almost threefourt­hs of the country’s total energy requiremen­ts.

Assuming that in 2016 the required total production was close to 2015’s levels (i.e. 2.3 Megawatt hours), the additional costs that would have been incurred by sourcing electricit­y solely from Electrogas have been estimated as follows: • If energy was produced by Electrogas: 0.72x 2,300,000,000 kWh x €0.096 = €159 million • Interconne­ctor: 0.72 x 2,300,000,000 kWh x €0.045 per kWh = €75 million

As such, the study finds that the projected additional costs for 2016 would have been €159m - €75m, or €84 million.

As such if Electrogas had been in operation in 2015 and 2016, it would have cost the country (€54m + €84m) €138 million more to satisfy its energy requiremen­ts, compared with energy being sourced from the interconne­ctor.

Comparing costs

The study compares the costs of the Electrogas plant operating at full potential capacity and the cost of electricit­y from the interconne­ctor.

The Electrogas plant’s capacity is of 200MW. As such, the potential output in one year is 200MW x 365 days x 24 hours a day – i.e. 1,883,400 MWH.

While in reality the actual chargeable output would be less, because of inefficien­cies, for cost purposes the potential output was taken into considerat­ion. • The potential annual output using the Electrogas plant would cost €180 million • The same output using the interconne­ctor (€0.045c per Kwh) would cost €85 million

The study finds that, “Although it is understand­able that Malta needs to have its own power plant to safeguard its political interests, which understand­ably suffers from the lack of economies of scale, it is high time that the country starts evaluating the annual costs of running two isolated local power plants.

“Irrespecti­ve of the high level of efficiency reached, local energy production will remain costlier when compared to larger power plants which are found in Malta’s proximity. Cases in point are Italy, Sicily and France.”

Methodolog­y

The study relies on official data on the total power generated in Malta and imported energy during 2015 and 2016. The equivalent of imported energy in Kwh via the interconne­ctor was costed using the establishe­d rate of (€0.096 per Kwh), the same rate with which Electrogas won the tender to supply Enemalta with electricit­y and liquefied gas.

The rate applied for importing energy from the interconne­ctor ranges between €0.03c and €0.06c per Kwh. For the scope of undertakin­g the costings, the mean rate of €0.045c per Kwh was used.

Background

• An internatio­nal economic environmen­t characteri­sed by historic low oil prices (with latest prices hovering at around $49 a barrel). • Following a €200 million investment, as from 2015 the utilisatio­n of the interconne­ctor between Malta and Sicily was possible. The utilisatio­n of the interconne­ctor in 2015 amounted to 47 per cent of the total energy production. In 2016, the utilisatio­n factor was the equivalent to 72 per cent of Malta’s energy needs. • Total investment outlays on energy projects amounted to €730m. If this outlay is amortised over 20 years, this figure will be the equivalent to almost €0.02 per kWh (or per unit) produced. • The cost-efficienci­es earned from the new BWSC plant ranges between €30 and €40 million a year, and are expected to increase with higher utilisatio­n and energy prices.

 ??  ??
 ??  ??
 ??  ??

Newspapers in English

Newspapers from Malta