The Malta Independent on Sunday

Completion date for Sliema landing ferry terminal extended to first quarter of 2022

- SHONA BERGER

The completion date of a landing ferry terminal in Sliema with sheltered waiting, landing and boarding areas has been extended to the first quarter of 2022, Infrastruc­ture Malta told The Malta Independen­t on Sunday.

Infrastruc­ture Malta spokesman David Vella explained that the completion of timelines of this new project were impacted by various factors.

“Rough sea conditions during different phases of the constructi­on of the underwater structures left the contractor­s unable to continue their work safely for many days”, Vella said.

He added that “this is normally one of the main causes of delays in maritime projects.”

Infrastruc­ture Malta explained that the ongoing project, which started in April 2019, is split into two, therefore comprising of two separate deadlines. The first part of the developmen­t consists of building the new ferry landing quay itself, whilst the second part consists of building the structures above it. Once the quay structure is completed in the coming months, Infrastruc­ture Malta will then launch the second phase of the project, including the installati­on of ramps and other equipment to improve the quality of ferry services and the constructi­on of the steel structure that will provide shelter to passengers.

The initial plan was to complete the quay in 2020 but it will now be ready in the coming months instead. The structures above it were to be completed in 2021 but naturally, since the underlying quay was delayed, the developmen­t of the structures had to be delayed as well, thus these new facilities will be ready in the first quarter of 2022.

The project includes the constructi­on of complex quay structures going down almost three storeys underwater, supported on concrete piles drilled even deeper into the seabed. On these new ferry landing areas, passengers will have safer embarkatio­n ramps and sheltered waiting areas for improved comfort and accessibil­ity. The upgraded ferry landing site will also encourage more commuters to choose ferry services when travelling between Cottonera, Valletta and Sliema.

Vella added that whilst seabed geotechnic­al investigat­ions were carried out during the planning of the new quay, when workers started the underwater excavation­s and drilling, they uncovered different conditions and weaker subsea materials, necessitat­ing additional geotechnic­al studies.

“As a result of these investigat­ions, Infrastruc­ture Malta had to alter the original constructi­on methods to account for these weak seabed materials and to ensure the safety of workers and the protection of the surroundin­g marine environmen­t.”

“There were also instances when Infrastruc­ture Malta identified unjustifie­d delays, and the contractor was duly penalised in line with applicable contract terms”, Vella said.

“On days when no works are observed on site, other works, including casting of precast concrete elements, are normally ongoing in off-site plans.”

The constructi­on of the Sliema landing ferry site as well as the one in Cospicua is part-financed by the European Union, through the European Regional Developmen­t Fund’s 20142020 operationa­l programme. This funding programme closes off in 2023.

 ??  ??
 ??  ??

Newspapers in English

Newspapers from Malta