Bay of Plenty Times

‘A genuine sense of relief’: Principal

School celebrates the opening of new teaching block

- Emma Houpt

“Agenuine sense of relief”. That’s how Taumata School principal Gen Fuller felt when more than 200 students started learning in a newly built teaching block at the start of this term.

The school is one of many in the Bay of Plenty-waiariki region that has Ministry of Education-led building projects under way at the moment — with a total budget of $200 million.

Ministry of Education data supplied to the Bay of Plenty Times under the Official Informatio­n Act shows constructi­on for the new teaching block at the school had an initial forecast completion date of quarter four of the 2021/22 financial year.

But the end date had been pushed out to quarter one of 2022/23.

It comes as the Western Bay of Plenty Principals Associatio­n president shared concerns about the delivery of property projects.

The OIA also reveals the budget for all Ministry-led projects under constructi­on in the Bay of Plenty-waiariki education region is around $200m, with the total spend standing at roughly $80m.

Fuller said the new teaching block was internally complete, with 211 senior students moving into the learning spaces on the first day of Term 3.

Fuller said there was a “genuine sense of relief” to have spaces that supported “desired learning pedagogy” and room for students to spread out.

She said the new teaching block had made a “big difference” to student wellbeing.

“The fact that there is space to enact learning — particular­ly for emerging adolescent­s,” she said.

“We are better able to deepen the learning experience, particular­ly in regards to project-based learning — the spaces are purposeful­ly designed to support active, messy, collaborat­ive, authentic learning.”

Work on the exterior of the new buildings and landscapin­g continued on-site, and it still needed to get signoff.

It was expected that these external works would be completed by midterm.

She said “extraordin­ary growth” since the school opened in February 2019 meant some classes were in the hall, library and administra­tion and staff room areas.

Stage 1 of the school was built for 390 pupils, but in 2020, Stage 2 of the project was expedited due to the “rapid” growth in the area.

The school’s current roll stood at 595 and would grow to 619 by mid

term, she said.

Fuller said a review of the master plan and negotiatio­n of the second build stage resulted in early design delays for Stage 2 of the project.

Covid-19 had impacted “on-site readiness” and access to constructi­on staff, she said.

“As a school, we have worked hard to mitigate the impact on teaching and learning — however, the underlying impact is that students have been accommodat­ed in spaces not designed for teaching and learning,” she said.

”[An] added impact has been the ability of our staff to come together in a common place due to the staffroom being utilised as a teaching and learning space,” she said.

Meanwhile, Western Bay of Plenty Principals Associatio­n president Suzanne Billington said the associatio­n was concerned about the delivery of property projects.

It had been “proactive” in trying to alleviate this issue, with a working group meeting regularly with the ministry.

“This is very much in its beginning stages, however it is being seen as a trial by the MOE that allows for current, credible, principal experience to be used with MOE staff to support overcoming these issues and building an improved and more transparen­t property system.”

Ministry of Education head of property Sam Fowler said it was working with the principals associatio­n to support the organisati­on in “delivering for the region’s schools”.

In the OIA, the Ministry said changes to the completion date could be due to a “range of issues”, including the impact of Covid-19 with supply shortages and contractor resourcing issues, or “project-specific delivery complexiti­es”.

In some instances, additional or amended stages changed the forecast completion date.

It was unable to provide the budgets broken down by school, saying these amounts were “commercial­ly sensitive” by nature.

 ?? Photo / Mead Norton ?? Taumata School principal Gen Fuller joins some of the students in the new teaching block.
Photo / Mead Norton Taumata School principal Gen Fuller joins some of the students in the new teaching block.
 ?? Photo / Mead Norton ?? Principal Fuller is overjoyed at the new teaching block.
Photo / Mead Norton Principal Fuller is overjoyed at the new teaching block.
 ?? ??
 ?? Photo / George Novak ?? Western Bay of Plenty Principals Associatio­n president Suzanne Billington.
Photo / George Novak Western Bay of Plenty Principals Associatio­n president Suzanne Billington.

Newspapers in English

Newspapers from New Zealand