DEMM Engineering & Manufacturing
Protect your pipelines from corrosion
In the petrochemical industry Corrosion Under Insulation (CUI) in pipeline systems consumes a significant percentage of the maintenance budget.
A large portion of this money is spent on expensive items such as external piping inspection, insulation removal and re-installation, painting and pipe replacements. CUI prevention strategies provide long term and reliable prevention of CUI that move towards inspection-free and maintenance-free piping systems and significant maintenance cost reductions.
Coating with TSA (thermal sprayed aluminium), using Metallisation flamespray equipment is one method that a number of operators within the petrochemical industry have adopted. TSA is found to be a cost effective solution compared to other systems when reviewed over the lifetime of the facility.
One of Metallisation’s customers has an ongoing programme for applying TSA at a petrochemical plant. One specific project is a marine jetty pipeline that is used for the transportation of lube oil and is exposed to the harsh marine environment. Other projects on this site have included a full range of pipes and vessels, including work on live operating plant.
To ensure the success of the thermal spraying process, the preparation of the pipeline surfaces is critical. For this project the pipeline surface was prepared by grit blasting with garnet to give a sharp angular profile for the TSA to bond to.
As part of the QA/QC process, the blast profile was regularly checked using Testex tape to ensure it meets the required 75-125 micron specification. The grit blasted surface was then given a visual inspection, using 10 x magnification, to check the surface cleanliness and finish.
The pipes are also given a ‘tape test’, which checks for dust contamination of the blasted surface. The tape sample is visually inspected against white and black backgrounds for signs of dust particles. The final quality test is a salt contamination test. Once all of these tests have been passed the pipelines are ready to be thermal sprayed with aluminium.
One advantage of the Metallisation equipment and process is the flexibility and long supplies, which provide a safe working environment and ease of use for the operators. In this project, the gas bottles and compressor were situated in a remote supply area, which gave easy access to the gas cylinders and enabled manifolding for fewer cylinder changes.
In elevated applications such as vessels and towers, the cylinders can remain on the floor while the spray system is elevated tens of metres. This situation therefore requires less complex scaffolding as the heavy bottles are not scaffold mounted. The 30 metre supply package, consisting of gas, oxygen and air, was fed from the overhead supply area down to the control panel.
The pistol is then a further 10m away from the control panel. This setup allows around a 60m length of piping to be sprayed without having to move the cylinders and air compressor, giving significant productivity benefits in a difficult environment.
The contractor on this specific jobsite is using two Metallisation MK73 flamespray systems in different spray locations. Once the blasting and inspection is completed, the TSA application starts. Typically, blasting and inspection is completed in the morning taking approximately four hours.
The TSA is applied in the early afternoon for around three hours and the final sealant application at the end of the day.
The MK73 deflected extension is perfect for those difficult to access areas commonly found at petrochemical sites, and has been designed specifically for this application area. It comes in three lengths, 150mm, 300mm and 450mm. The extension unit can spray directly forward or at a deflected angle up to 90º by varying the deflector air pressure.
The deflection nozzle can also be rotated through 180º to allow spraying in a 360º arc around the pistol.
Following the application of the TSA, the pipelines in this specific application were sealed with Intertherm 50 sealer, which was applied until full penetration was achieved. In some CUI related environments, no sealer is applied, especially where the spray area is operational and hot.
To support the QA/QC process the spray operators produced witness plates on a daily basis, which were then tested for adhesion to ensure it met the minimum 1000 psi – 6.9PMa coating thickness.
For more information on the CUI or thermal spray equipment see www.metallisation.com