Stormwa­ter up­grades planned to be com­pleted by July 2013

Arawhata St and Mexted Cres, Ranui (stage 2 of project). Cost: $112,000

Eskdale Rd and Con­clu­sion St, Can­nons Creek (stage 2). Cost: $80,000

Toms Rd, Ti­tahi Bay (stage 1). Cost: $180,000

Tireti Rd and Te Pene St, Ti­tahi Bay (stage 2). Cost: $140,000

Pikarere St (stage 1). Cost: $140,000

City­wide im­prove­ments (projects like grates be­ing in­stalled in sumps). Cost: $100,000