Manawatu Standard

Domain relief not till spring

- JANINE RANKIN

The cost of protecting the Ashhurst Domain from further erosion by the Manawatu River has been estimated at as much as $800,000, and none of it will be done before spring.

Hundreds of metres of the lower domain were swept away in flooding caused by the remnants of Cyclone Debbie in the first week of April.

It compounded damage that had occurred in two previous winters, to the disgust of local man Gary Tanner, who said the delays in acting to protect the banks were ‘‘incompeten­ce’’.

On Wednesday, Palmerston North City council City Networks general manager Ray Swadel will outline the proposed solutions and costs to councillor­s.

The options proposed by Horizons Regional Council range from $260,000 to $800,000.

Horizons is only prepared to contribute up to $80,000 of the costs, as the area is outside its flood-management scheme boundaries.

Swadel said there were still questions about why the 700-metre section of the Manawatu River, from where it joined the Pohangina River to the State Highway bridge, were outside the scheme.

Swadel said the erosion was continuing even during modest river flows and there was clearly a need to do some bank protection work as soon as possible.

But whatever solution was agreed, nothing could be done before September at the earliest.

‘‘The opportunit­y to work on the site has now been lost until the lower river flows in spring.

‘‘Horizons do not believe there are any interim works that can be undertaken to arrest the current erosion.’’

The cheaper of two options is a series of willow tree structures anchored with railway irons and wire-rope ties, to prevent erosion.

Horizons advice was that the structures, known as groynes, would need a high level of monitoring and maintenanc­e, and carried some risks of failure.

The more expensive option was rock lining of the exposed bank.

The works proposed would take four to six weeks to complete.

Given the limited budget available from Horizons, the costs to city council ratepayers could range from $182,000 to $720,000, or more.

The other potential source of money could be the New Zealand Transport Agency.

Late last year, the agency had considered advice that there was no immediate risk to the State Highway bridge approaches that would warrant it contributi­ng to the cost of bank protection.

However, the further erosion extending much closer to the western bridge abutment this month has prompted the agency to reconsider its decision.

Swadel said options would be discussed at a three-way meeting between the two councils and the agency. ‘‘The local community is expecting action regardless of which authority has jurisdicti­on over this matter.’’

City councillor­s will debate the progress report on Wednesday.

Newspapers in English

Newspapers from New Zealand