Marlborough Express

Breakthrou­gh in highway rebuild

- OLIVER LEWIS

For the first time since the earthquake, road crews working to reopen State Highway 1 have access all along the coastal route.

The last time anyone drove around Ohau Point was nearly a year ago, before the earthquake brought down thousands of tonnes of rock on the highway.

But that all changed on Monday, when crews working from the south and north converged in the middle to open up an access track around the base of the point.

A couple of slips still remain along the coast, and access around Ohau Point is limited to excavators, but nonetheles­s the ‘‘viable link’’ has been described as a major milestone.

Transport Minister Simon Bridges said the achievemen­t would help speed up the work to get SH1 open to the public by Christmas.

‘‘Constructi­on crews now have access to the entire stretch of the coastal corridor north of Kaikoura which will greatly speed up the reinstatem­ent of this important route,’’ he said.

Bridges said the North Canterbury Transport Infrastruc­ture Recovery (NCTIR) teams had cleared seven of the nine major slips that buried parts of the highway and railway line north of Kaikoura.

But getting access around Ohau Point, the largest and most technicall­y challengin­g slip, had long been the sticking point.

During the 7.8-magnitude earthquake more than 100,000 cubic metres of rock and debris slipped down the cliff face, burying the highway below.

To make it safe for ground crews, abseilers working at the top of the bluff bolted on 4500 square metres of steel ring net - the largest rockfall drape in New Zealand.

NCTIR coastal route realignmen­t constructi­on manager David McGoey described the access track as a foundation, one that would be used by excavators to form a safer track some 4 metres higher for light vehicles.

However, having any kind of access around the point was a big deal, as it meant machinery could be transferre­d from sites south of Ohau to slip seven, just north of the point.

‘‘It’s the first time there’s been a viable link for SH1, even though the only thing we can track across are excavators,’’ he said.

‘‘For the first time we can transfer a 50-tonne excavator from site six over to site seven. Whereas previously we would have had to have an eight or nine-hour journey around,’’ he said.

It also meant road crews based in Blenheim, who faced a 90-minute journey to sites just north of Ohau, could be based in Kaikoura, he said.

NCTIR earthworks manager Mike Reilly said having access around Ohau Point would make it far quicker to get machinery.

‘‘There’s been a lot of work to get it here, so it is a milestone.’’

 ?? PHOTO: SUPPLIED ?? Excavators working from either side of Ohau Point meet in the middle to open an access track for the first time since the earthquake.
PHOTO: SUPPLIED Excavators working from either side of Ohau Point meet in the middle to open an access track for the first time since the earthquake.

Newspapers in English

Newspapers from New Zealand