Nelson Mail

Big cleanup complete

- Tim O’Connell tim.oconnell@stuff.co.nz

The cleanup of one of New Zealand’s most contaminat­ed sites is now complete.

The $8.9 million remediatio­n of Port Nelson’s Calwell Slipway came to an end last week, winding up an eightyear process to fix pollution caused by years of shipping repair work that used toxic substances.

Project manager Kelly Leonard, of Port Nelson Ltd, said she was pleased to have the task finished, with only minor weather delays and maintenanc­e hampering the progress of the remediatio­n team.

Leonard said the project would come in under budget.

‘‘It was pretty complex, but now we’re at the end.’’

The Ministry for the Environmen­t’s Contaminat­ed Sites Remediatio­n Fund (CSRF) provided 50 per cent of the project’s funding.

The slipway site was ranked number two on the CSRF list prior to the project. Marine sediments around it were contaminat­ed by pollutants such as tributylti­n and copper from ship repair work dating back to 1970.

Work began in October last year. The project, managed by Port Nelson and carried out by Auckland-based civil engineerin­g contractor­s Heron Constructi­on, used excavators and dredging equipment to dig up the contaminat­ed sediment. This was mixed with concrete and bound with activated carbon to form ‘‘mudcrete’’, which contained the pollutants, before being returned to the seabed.

The final 1000 cubic metres was dredged in April.

Last week Heron Constructi­on completed site disestabli­shment and restoratio­n of the slipway and surrounds, finished off with rocks being placed on the reclamatio­n face.

Target concentrat­ions for residual sediments in the Calwell Slipway Basin were 270 mg/kg for copper and 0.07mg/kg for tributylti­n. Sampling at the conclusion of site works showed 42mg/kg for copper and 0.039mg/kg for tributylti­n.

The second objective was to restore navigabili­ty to the Calwell Slipway Basin, which had not been dredged since 1984. A post-dredge hydrograph­ic survey has indicated that charted depths have been restored and exceeded in many locations within the basin.

A new 5000-square-metre reclamatio­n was constructe­d east of Kingsford Quay adjacent to the slipway. Leonard said the reclaimed land would be paved in spring to be used for additional log storage

‘‘It was pretty complex, but now we’re at the end.’’ Project manager Kelly Leonard

Speaking to Stuff in December, Port Nelson chief executive Martin Byrne said the project was a ‘‘winwin’’ for the port, cleaning the slipway as well as creating extra land to reconfigur­e log storage areas.

Leonard said the slipway would remain on the CSRF website until it was updated with the next funding round announceme­nt.

From the port’s perspectiv­e, however, it was mission accomplish­ed.

‘‘In terms of monitoring, there’s not much there to monitor, so we don’t have any ongoing obligation­s.

‘‘Now all discharges from the slipway are contained and disposed of appropriat­ely . . . and with the worldwide ban on [tributylti­n], we’re not seeing it in circulatio­n any more.’’

 ?? BRADEN FASTIER/STUFF ?? Project manager Kelly Leonard at the site of the $8.9 million remediatio­n of Port Nelson’s Calwell Slipway, which was once one of the most contaminat­ed sites in the country.
BRADEN FASTIER/STUFF Project manager Kelly Leonard at the site of the $8.9 million remediatio­n of Port Nelson’s Calwell Slipway, which was once one of the most contaminat­ed sites in the country.
 ??  ??

Newspapers in English

Newspapers from New Zealand