Nelson Mail

Fronting up over Greenmeado­ws

- Sara Meij, Skara Bohny and Amy Ridout

The company subcontrac­ted to work on the Stoke Greenmeado­ws project is no longer trading.

The main contractor, Auckland constructi­on company Watts & Hughes, fronted up to media questions yesterday about shoddy workmanshi­p at the site and said delays were due to the subcontrac­tor’s performanc­e.

TCT Ltd were employed after the previous subcontrac­tor, Canstruct Interiors, went into receiversh­ip. No TCT workers have been seen on site since Tuesday morning.

Watts & Hughes regional manager Dave Gamlen said TCT stopped trading because it couldn’t pay its staff.

He said he believed both Canstruct Interiors and TCT used the same staff to work on Greenmeado­ws.

Watts & Hughes director Rob Murphy it was not unusual to continue with the same workers on a project. It had used the subcontrac­tors before on projects in Christchur­ch and had not had any problems with them.

However, other subcontrac­tors working at the site raised questions about the build quality and constructi­on delays.

They said the subcontrac­ted company’s workforce comprised mostly unqualifie­d, unskilled labourers from the Czech Republic, and there had been incidents where labourers had asked for help from local subcontrac­tors. Watts & Hughes confirmed that some of the workers had been apple pickers.

‘‘They were pushing the broom, they weren’t employed as carpenters.’’

Watts & Hughes said any poor quality work will be rectified and has admitted it will end up out of pocket due to constructi­on issues at the site.

It will be bringing in workers from Christchur­ch and Auckland to finish the building to the standard it was contracted to.

‘‘We have a reputation, we live on that reputation.’’

It was unlikely to tender for Nelson civic projects in the future.

When pressed about the subcontrac­tors’ skills and qualificat­ions, Murphy said Watts & Hughes had no concerns.

However, Gamlen admitted there were communicat­ion problems between his firm and the subcontrac­tors, particular­ly in regards to the exterior cladding, which had to be replaced at a cost of thousands of dollars.

‘‘[Instructio­ns] weren’t conveyed adequately from our site staff to the site contractor­s. It’s an error that’s costing us a lot of money.’’

Murphy also addressed concerns about subcontrac­tors not being paid in the past, and said Watts & Hughes was up to date with their payments.

‘‘Subcontrac­tors ... will be paid, there’s no problem there at all.’’

Watts & Hughes said any money owed to accommodat­ion providers by the subcontrac­tors would need to be met by those subcontrac­tors.

Mayor Rachel Reese said she was ‘‘extremely disappoint­ed’’ around the constructi­on process and the Stoke community deserved a better process, but promised that Greenmeado­ws would be finished to a good quality.

‘‘This is a project for the Stoke community,’’ she said.

‘‘As mayor, on behalf of the Stoke community I am disappoint­ed in the building process, but they will get an outcome that they can be proud of.’’

She said an audit would be carried out by independen­t building consultant Grant Hunt.

‘‘It’s not that I think there’s anything untoward going on, it’s just a matter of due diligence,’’ she said.

Reese said that when approving budgets, council took into account whether or not potential unexpected events had been taken into account.

She said in this case, not enough contingenc­y had been built into the budget.

Infrastruc­ture group manager Alec Louverdis said the aim was still to ‘‘deliver a facility that is of the highest standard’’.

Louverdis agreed that unexpected costs, such as the removal of asbestos from the old tennis courts, were higher than expected.

‘‘We have learned lessons from this,’’ he

‘‘We have learned lessons from this. The contingenc­y on this project was too low.’’

Nelson City Council infrastruc­ture group manager Alec Louverdis

said. ‘‘The contingenc­y on this project was too low.’’

Watts & Hughes won the tender in June 2016, undercutti­ng local firms with a $4.6 million bid. Other tender bids ranged from $5.4m to $6.6m.

Watts & Hughes said their tender bid at the time was a realistic offer.

The budget was originally set at $6.15m, however, this has since increased to $7.19m.

Louverdis said it was because of additions to the original design, such as the kitchen, and because of variations to the design requiring input from architects and other profession­als.

 ?? BRADEN FASTIER/STUFF ?? Watts & Hughes constructi­on director Rob Murphy talks to the media during a press conference held by Nelson City Council regarding the constructi­on of the Greenmeado­ws Community Centre in Stoke.
BRADEN FASTIER/STUFF Watts & Hughes constructi­on director Rob Murphy talks to the media during a press conference held by Nelson City Council regarding the constructi­on of the Greenmeado­ws Community Centre in Stoke.
 ?? BRADEN FASTIER/STUFF ?? Nelson Mayor Rachel Reece and councillor Gaile Noonan take part in the Greenmeado­ws press conference with Watts & Hughes constructi­on director Rob Murphy and regional manager Dave Gamlen.
BRADEN FASTIER/STUFF Nelson Mayor Rachel Reece and councillor Gaile Noonan take part in the Greenmeado­ws press conference with Watts & Hughes constructi­on director Rob Murphy and regional manager Dave Gamlen.

Newspapers in English

Newspapers from New Zealand