Fears over budget and build
THE NEW Dunedin Hospital will be over budget and there are serious doubts whether the first of its two buildings will open on time, a Cabinet paper says.
The paper, released to the Otago Daily Times under the Official Information Act, also revealed Treasury opposed the Cabinet decision in September to approve in principle the detailed business case (DBC) for the hospital.
Treasury comment on the Cabinet paper said the project’s DBC lacked sufficient detail and required significant additional work to enable a proper investment decision to be made.
‘‘The new Dunedin Hospital is the most expensive and complex vertical health infrastructure project ever undertaken in New Zealand and it is important that sufficient work is conducted through the detailed business case phase to ensure that the project is deliverable to timetable, that risks are adequately managed, and benefits of the project are realised.’’
The Cabinet paper, brought by Health Minister Chris Hipkins, said the $1.4 billion budgeted for the hospital would be insufficient.
‘‘Additional funding will be requested at the time a budget is set as part of the revised detailed business case, to be completed for Cabinet by February 2021.’’
Mr Hipkins said there were grave doubts whether the first of two proposed buildings in the complex, the inpatient building, could open in 2028 as intended.
‘‘Further work is needed to ensure all risks are identified and quantified prior to contract execution given the scale, programme and interface issues associated with the contract.
‘‘For instance, while labour initiatives such as Workforce Central will assist, it is also clear that deliverability of this major hospital in Dunedin remains a concern, in particular the scale of labour force required to deliver the inpatient building by 2028, an estimated 9001000 workers.’’
Treasury said Cabinet agreement to a complete detailed business case was the standard expected of all major Crown projects, but it recognised the importance of maintaining the momentum of the project.
It recommended noting the DBC as a draft, but said even to do that was risky.
‘‘The lack of a quantitative risk assessment and more detailed concept designs will mean that standard assurances around costings, contingencies and approaches to cost risk management are missing.’’
The DBC as presented also did not adequately consider the impact of Covid19 on the project, particularly on recruitment, Treasury said.
‘‘Whilst there is a significant effort to recruit and train local staff, it is not clear that this will be to the scale necessary to overcome any workforce shortages.’’
Mr Hipkins said it was critical the project proceed without delay. Cabinet decided before the election to give inprinciple approval to the DBC and released $127 million for early work.