Power project brings workers south

IDA VALLEY

- JARED MORGAN jared.morgan@odt.co.nz

A HIGH wire act is unfolding high above the Ida Valley as work to rewire the national grid from Roxburgh in Central Otago to Livingston­e in the Waitaki district continues.

The work encompasse­s a $100 million investment in Transpower’s Clutha Upper Waitaki Lines Project (CUWLP) to upgrade from ‘‘simplex’’ to ‘‘duplex’’ — from single to double wires — on the Roxburgh to Livingston­e section of the RoxburghIs­lington 220kV line and a thermal upgrade of the Cromwell to Twizel section of the RoxburghTw­izel 220kV line.

The work is being undertaken by about 70 transmissi­on and distributi­on line mechanics from across New Zealand (the majority from Palmerston North) from Electrix who provide the grunt behind the extra juice.

Distributi­on line mechanic Zander Whitman said that along with with line duties, he was based at a tensioner site — a mobile base where the new lines were tensioned between towers (pylons).

The work involved one phase per day, going from one to two lines, for a total of three phases, or six wires.

The sites remained in place for three to four days before moving up the line, giving Mr Whitman time to take in Central Otago’s scenery, he said.

‘‘I’m falling in love with this [landscape] now. I want to bring my wife to see it.’’

Also at the site was mechanic supervisor Damian Durban, who said it was his second time in the South Island.

He had worked on a similar lines project between from Ashburton to Oamaru — it was in Canterbury that he encountere­d snow for the first time.

Down the line towards Poolburn, a team of four transmissi­on and distributi­on line mechanics were engaged in the acrobatic work of removing the blocks — large reels the lines are rolled through — to attach the lines to the insulators.

Flynn Wild said in his two years on the job, the skill of walking on wire had become second nature.

Crewmate Marbert Nero said on a good day, communicat­ion between himself and the ground was easy; wind made it difficult and sometimes they had to resort to hand signals.

Fellow crew member Scott Mulcahy agreed.

‘‘In the wind they can’t hear a thing from us on the ground.’’

Transpower CUWLP project director Roy Noble said work was under way in the northern end of Ida Valley near Oturehua, and work was expect to be completed from there Naseby by early May.

Then, the workers would head back to the Poolburn area to complete a 10km section before disestabli­shing for winter, he said.

In early October, Transpower would return to complete a 12km section between Earnscleug­h and Galloway Rd through the Alexandra area.

That work was expected to be completed by the end of November.

In January 2022, work would begin on the NasebyDans­eys PassLiving­stone section, and the intention was to complete this section by the end of April, Mr Noble said.

to

 ?? PHOTOS: JARED MORGAN ?? Linemen for a different county . . . Electrix transmissi­on and distributi­on line mechanics Scott Mulcahy (left) and Sean ‘‘Stewie’’ Stewart on site in the Ida Valley.
PHOTOS: JARED MORGAN Linemen for a different county . . . Electrix transmissi­on and distributi­on line mechanics Scott Mulcahy (left) and Sean ‘‘Stewie’’ Stewart on site in the Ida Valley.
 ??  ?? Walking on wire . . . Electrix transmissi­on and distributi­on line mechanics Marbert Nero (left) and Flynn Wild show little fear of heights at the top of a pylon in the Ida Valley.
Walking on wire . . . Electrix transmissi­on and distributi­on line mechanics Marbert Nero (left) and Flynn Wild show little fear of heights at the top of a pylon in the Ida Valley.
 ?? PHOTOS: SUPPLIED BY WAITAKI DISTRICT COUNCIL ?? Contaminat­ed . . . General waste has been dumped among recycling at the Enfield Recycling Centre again.
PHOTOS: SUPPLIED BY WAITAKI DISTRICT COUNCIL Contaminat­ed . . . General waste has been dumped among recycling at the Enfield Recycling Centre again.

Newspapers in English

Newspapers from New Zealand