Feasibilit­y study into hydro scheme: phase 2

- STAFF REPORTER

INVESTIGAT­IONS into the viability of a battery project at Lake Onslow have moved to private land and a catchup with the local community is planned.

The $4 billion project is still in the investigat­ion phase and informatio­n was expected to go to Cabinet at the end of the year.

An initial phase of fieldwork in Teviot Valley began in June. This fieldwork was located on public land, such as road reserves, at two main sites and was completed this month.

The initial work was investigat­ing where on the Clutha River water could be stored before being pumped through a tunnel to Lake Onslow. Depending on the location, this may involve the constructi­on of a lower reservoir.

A lower reservoir would allow the pumped hydro scheme to take and return water and minimise any effects on the river.

The feasibilit­y study had identified three possible areas for a lower reservoir — one at Lake Roxburgh where the lake would act as a reservoir, and at two sites further downstream.

More informatio­n was needed to help determine the most appropriat­e location, size and design for a lower reservoir, should the scheme go ahead. Landowners would be contacted who may be affected by the planned reservoir.

A second phase of geotechnic­al work would begin at a new site on private land in the Teviot Valley at the end of this month. This work is an extension of the fieldwork in the Teviot Valley.

This location has been selected for its nearsurfac­elevel geological features, which provide insight that can inform the broader design work of the proposed pumped hydro scheme.

This second phase of fieldwork is expected to take about four weeks.

Once the onsite work was complete, the drill holes were covered and the area was rehabilita­ted. The groundwate­r levels and pressure at some sites were remotely monitored. At these sites, a small, fenced structure enclosed the covered drill holes and a 5m pole with solar panels and dataloggin­g equipment were installed.

Once the work finished and the site rehabilita­ted, a small area around the covered drillhole is fenced off. A small solar panel, monitoring equipment and telecommun­ications equipment is installed so groundwate­r data can be collected and monitored remotely.

Over time, all areas where the ground has been disturbed will be rehabilita­ted, leaving little to no evidence of activity.

A dropin event for the community was planned for October 29, and it would be a chance to hear more about the project and talk more with members of the project team.

It was revealed last month there was enough elevated water storage for the project’s upper reservoir and the surroundin­g land was strong enough to support the building of a dam. Transmissi­on lines were big enough near the site to transmit power.

The Clutha River was also sufficient­ly lower in altitude than Lake Onslow with enough water to pump from and had suitable tunnel and lower intake options.

 ?? PHOTO: ODT FILES ?? Lake Onslow . . . Proposed battery project may involve constructi­on of a lower reservoir at Lake Roxburgh or further downstream.
PHOTO: ODT FILES Lake Onslow . . . Proposed battery project may involve constructi­on of a lower reservoir at Lake Roxburgh or further downstream.