The New Zealand Herald

Power plan: Winners and losers

Charging change calculated to give savings of about $2.7b over 30 years, says authority

-

Changes proposed to the way electricit­y transmissi­on costs are shared could deliver about $2.7 billion in benefits to consumers during the next 30 years, the Electricit­y Authority says.

The plan, which aims to charge consumers based on the benefit they receive from transmissi­on projects, will increase costs for many large industrial power users on the North Island, but will generally lower costs for South Island generators and lines companies in the lower South Island and lower North Island.

Homes and business in areas facing increases, such as Auckland and Northland, would initially pay an extra $21 a year on average, with increases capped at no more than 3.5 per cent. In 12 regions consumers’ costs would fall by about $20 a year.

Among generators, Meridian Energy remains the biggest potential beneficiar­y with a projected $29 million fall in its transmissi­on costs in 2022, while Mercury NZ faces the biggest generator increase at $6.6m.

Authority chief executive James Stevenson-Wallace says most of the estimated national benefit — more than $2.3b — comes from lowering the cost of electricit­y use at peak times by removing a peak charge Transpower applies under the current transmissi­on pricing methodolog­y, or TPM.

Better price signals are expected to deliver improved decisions on generation investment and see grid-scale batteries used efficientl­y — instead of just for avoiding transmissi­on costs. Those benefits could be worth another $350m.

“Under the current TPM, customers are investing in alternativ­es — such as batteries — to avoid paying the peak charge, which wastes resources and shifts the cost of operating and maintainin­g the grid to others,” Stevenson-Wallace said.

“This avoidance is likely to increase if the TPM is not amended, as more grid investment­s are made to support the shift to a low-emissions economy — and batteries and distribute­d generation become more affordable.” The industry has been debating improvemen­ts to transmissi­on pricing for a decade. Some changes have already been made, freeing up generation in the South Island and removing transmissi­on subsidies from small, regional power stations unless those plants provided a network benefit.

But the main issues — charging all of the $145m annual cost of the highvoltag­e link across Cook Strait to South Island generators, and smearing the costs of major transmissi­on projects across all consumers whether they benefited or not — remain unresolved.

The EA says the country needs more renewable generation, yet potential South Island generation projects are being disadvanta­ged by an effective “tax” increasing their costs by about 10 per cent.

Leaving firms and households in most of the South Island and parts of the North Island paying for — but getting little benefit from — more than $2b that was invested in the past decade upgrading the power link across Cook Strait, the lines around the Wairakei geothermal fields, the lines from Whakamaru into Auckland, is also adding further risk.

The scheme proposed yesterday is little changed from that proposed in 2016, when the authority had also proposed a cap on the annual impact the change could have on households.

But the benefits and costs are generally smaller, as falling interest costs mean transmissi­on charges will be much lower — about $848m in 2022 when the change could take effect — down from about $950m today and less than had been projected in 2016.

Where Auckland power distributo­r Vector, a vocal opponent of the change, had in 2016 faced a potential increase in its transmissi­on costs of $59m, today’s proposal would see those costs rise in 2022 by $7m.

The Tiwai Point aluminium smelter, which was expecting a $20m benefit, will likely be $11m better off than would otherwise be the case in 2022.

The authority is receiving submission­s on its proposals until October 1. It plans to make a final decision early next year.

 ?? Photo / NZME ?? Most of the projected savings would come about by removing a peak-time usage charge applied by Transpower, the authority says.
Photo / NZME Most of the projected savings would come about by removing a peak-time usage charge applied by Transpower, the authority says.

Newspapers in English

Newspapers from New Zealand