$104m cathedral rebuild will take years to complete

Building has long stood as a symbol of the lack of progress on city’s reconstruc­tion

- Logan Church

Work to reinstate the Christchur­ch Cathedral is now well under way, but it could be eight years before it reopens. The cathedral was damaged in the September 2010 earthquake and reopened soon after. However, the February 2011 earthquake devastated the building.

The cathedral lay in ruins for years while a decision was made as to what to do with it. In 2017 the Synod voted — by a narrow majority — to reinstate the building. This came after the then-National government offered a $10 million cash contributi­on and a $15m loan — a $10m grant was also pledged by the Christchur­ch City Council.

The building had long stood as a symbol of the lack of progress on the city’s rebuild, but now, more than 10 years after the first earthquake, work is well under way on the site, overseen by the Christ Church Cathedral Reinstatem­ent Trust.

The Herald was taken on a tour of the cathedral site by project director Keith Paterson to see what work was being done. Much of that work involved stabilisin­g the structure.

At the front of the building — the west wall — timber bracing had been put up. That wall, including its large rose window, collapsed following the quakes. Facing timber had also been installed in preparatio­n for permanent stabilisat­ion frames.

On the southwest transept, the first part of stabilisat­ion work was under way. That involved creating heavy foundation­s to support steel frames that would reach to the top of the transept.

Then, long steel bars would be drilled into the wall to connect the frames to the building — core samples had been taken from the wall to check for voids.

Gaps in the building would also be weatherpro­ofed.

On the other side of the building, similar work was being completed, with large foundation­s put in place to support a structure that would clamp on to the building.

Paterson said the building also needed to be cleared of vermin.

“We have a pigeon problem.

The nature of the work is artisan and it’s not convention­al constructi­on . . . and that is why it’s a wee bit tricky to predict just exactly how long it will take.

Keith Paterson, project director

Unfortunat­ely they have inhabited the building for the last eight years and have contaminat­ed it.”

Pigeons were not the only natural encroachme­nt that had to be dealt with — parts of the roof had collapsed on the northern side of the building resulting in “an internal garden”.

Aside from the stabilisat­ion work, efforts were being made to preserve the heritage of the building — including its contents. Heritage profession­al and cathedral lay canon, Jenny May, was able to enter parts of the building alongside Urban Search and Rescue (USAR) in the weeks following the quake to retrieve some items.

“All of our silver chalices . . . our procession­al crosses, the bishop’s crosier . . . things that were very important to the church,” she said. But much remained. “There is a huge range of material that is in there — there is also a lot of material the condition of which we don’t know because a lot of rubble was moved around in the nave by USAR when they were making sure nobody had been killed or trapped.”

Part of May’s job involved making sure items found in this stage of the reinstatem­ent were carefully removed, recorded, and stored.

She said there had been some “incredible” finds along the way, including pieces of the intricate rose window that sat in the west wall.

“I was standing with the stonemason . . . he was going through one pile, I was going through another, he held up a piece and said to me ‘look at this’ and I said ‘ I think I’ve found the other half of this’ . . . he handed it to me and we put them together and we had a whole face,” she said.

There was still a big question mark over how much the project would cost. An estimate in 2017 was around $104m, made up of the church’s insurance money, the Crown and council contributi­ons, grants, and fundraisin­g efforts.

The former Anglican bishop, Victoria Matthews, initially wanted to demolish it and build a replacemen­t, at the time saying there were much greater concerns facing the church, including child poverty and climate change.

It was expected the final cost would be more than $104m and while Paterson would not say what the updated cost figures were, he said that informatio­n would be released next month.

He said it was also not possible to state a firm timeframe for how long the work would take.

“The nature of the work is artisan and it’s not convention­al constructi­on. As a result, one thing has to be done before the next and that is why it’s a wee bit tricky to predict just exactly how long it will take . . . but my best estimate is about seven to eight years.

“At the moment sitting here in the square is a symbol of a lack of progress — what we can see is progress has started.”

 ?? Photo / Logan Church ?? A face rescued from the rose window of the Christchur­ch Cathedral, which was left in ruins after the February 2011 quake.
Photo / Logan Church A face rescued from the rose window of the Christchur­ch Cathedral, which was left in ruins after the February 2011 quake.