Ahuge column of steam could be seen rising near Kaikohe yesterday as testing began of the first production well for a new power station.

Far North power company Top Energy is building a geothermal power station at Nga¯wha¯ which could eventually make the Far North selfsuffic­ient in electricit­y and even an energy exporter.

The company already operates a geothermal power plant at Nga¯wha¯ —

New Zealand’s biggest geothermal field after the Central Plateau — producing 25MW of power. The new plant will more than double that to 53MW.

Top Energy chief executive Russell Shaw said testing of the first new production well started on Monday with encouragin­g results. The tests involved the controlled release of geothermal fluid from the well, which caused steam to be released into the atmosphere.

Shaw said the steam could look alarming but was harmless and not a cause for concern.

Hot water produced by the tests was collected in ponds before being pumped back into the ground.

Testing would continue on and off for several weeks, he said. The drilling is being carried out by Iceland Drilling, an Icelandic company with expertise in geothermal wells.

The drilling rig arrived at Northport on April 25 and took six days and 60 truckloads to transport to Nga¯wha¯.

Five 1750m-deep wells will be drilled for extraction and re-injection. Each well takes about 30-40 days of 24-hour-a-day drilling.

The new power station will cost $168 million and is due for completion in 2021.

If all goes well, Top Energy will build a third plant by 2025, boosting total production to 81MW. Peak power consumptio­n on cold winter evenings in the Far North is around 70MW.

The new plant, like the original power station, will be built by an Israeli company but assembled on site by local contractor­s. The earthworks contract went to Whangarei-based United Civil Constructi­on.

Council-owned company Far North Holdings plans to develop an industrial park across State Highway 12 from the power station.

 ?? Photo / supplied ?? A column of steam rises above the drilling site at Nga¯wha¯ where a new geothermal power plant is due to be built by 2021.
Photo / supplied A column of steam rises above the drilling site at Nga¯wha¯ where a new geothermal power plant is due to be built by 2021.
 ??  ??

Newspapers in English

Newspapers from New Zealand