Kerikeri wastewater plant delays

Residents frustrated with delays on plant that have been going on for around three years

- Local Democracy Reporter Susan Botting

Angry Kerikeri residents say they have no faith their town’s new $27 million wastewater treatment plant will be working by January. “We were told by Far North District Council we would have reticulate­d sewerage to our properties by the end of 2017,” Jane Johnston, Kerikeri Residents and Ratepayers Associatio­n president, said.

There had been ongoing updates on that since then, none of which had happened, Johnston said.

“There have been ongoing delays that are affecting the Kerikeri economy.”

In August last year, the Northern Advocate reported the plant was to have been completed by December 2019. By December, FNDC said the plant was to be completed in April 2020.

Its latest forecast now has the plant due to be finished by the end of September.

The Northern Advocate also reported in the same article that Kerikeri households and businesses were expected to be able to connect to the scheme by July this year.

By December last year, FNDC said this would happen in September this year, but January next year is now the latest forecast.

The plant’s project delivery performanc­e was part of an update in FNDC chief executive Shaun Davidson’s report to the council’s meeting last Thursday.

This showed the plant red-carded on all five project plan performanc­e target indicators. It failed to achieve across all targets, including project completion status, the scope for the project growing, its rates of progress and costs tracking.

Andy Finch, FNDC general manager infrastruc­ture and asset management, said performanc­e on those indicators was not unexpected for a project of the plant’s size.

The indicators and their milestones had been set up at the start of the project. There had been a lot of changes since.

Indicators presented to the meeting showed a “fairly pessimisti­c” view of what would be a successful project.

“I don’t think this metric does it any justice,” Finch told councillor­s.

The report said the scope of the project had expanded due to design issues because the contract had been let without “issued for constructi­on” drawings. These are detailed design drawings integral to assessing exactly what work is to be involved in a contract.

There were also significan­t impacts on the project’s completion schedule, from addressing health and safety compliance issues identified through project risk assessment.

Johnston said delays had meant continued trucking of some of Kerikeri’s sewage to Kaikohe for processing.

They had potentiall­y impacted on the area’s water quality as people held off upgrading septic tanks in expectatio­n of being able to go onto a reticulate­d wastewater system.

Developmen­t was affected, sometimes illogicall­y, Johnston said. Residentia­l subdivisio­ns in the new areas to be brought into the scheme could not go ahead while those in areas outside the scheme could.

FNDC said the new plant would triple the amount of wastewater treated by the town’s existing Shepherd Rd plant. In December last year, it said this plant was due to be shut down in October. The council said the new scheme would serve all properties already connected to Kerikeri’s wastewater system plus 350 new properties on septic tanks. It will also have the capacity to serve 400 further properties and is designed for expansion to provide for further growth.

We were told by Far North District Council we would have reticulate­d sewerage to our properties by the end of 2017. There have been ongoing delays that are affecting the Kerikeri economy.

Jane Johnston, Kerikeri Residents and Ratepayers Associatio­n president

 ?? Photo / FNDC ?? One of 70 pre-cast concrete panels for Kerikeri’s new wastewater treatment plant last year.
Photo / FNDC One of 70 pre-cast concrete panels for Kerikeri’s new wastewater treatment plant last year.
 ??  ??