The Northland Age

Aquifer consent delays costing jobs

- Peter de Graaf

Acompany investing tens of millions of dollars in avocado orchards in the Far North says jobs are being lost and investment put at risk because Northland Regional Council is “dragging its heels” on water-use consents.

That is denied by the council, which says historical aquifer level errors and the Covid-19 crisis caused the delays, and that consent hearings will start late next month.

Ground water use has become a contentiou­s issue in the Houhora area where 24 landowners have applied to take up to 6.4 million cubic metres a year from the Aupo¯ uri Aquifer.

A total of 113 submission­s have been received with most opposed to increased water take.

The applicatio­ns are from avocado growers who say the amount applied for is a fraction of the water entering the aquifer each year, and that converting pasture into orchards means many more jobs in the cashstrapp­ed Far North.

One of the biggest investors is Mapua Orchards, which is developing more than 400ha around Houhora and Waiharara.

General manager Ian Broadhurst said the company had taken a multimilli­on-dollar leap of faith ahead of new water permits being granted but the council seemed intent on “dragging its heels”.

As the process dragged into its third year, orchards were renegotiat­ing existing, smaller water consents to keep seedlings alive and cutting back expansion plans, he said.

Years’ worth of hydrologic­al work had shown the requested water take was a fraction of aquifer recharge, and fell well within allocation levels allowed in the regional plan.

“We can’t do anything without water . . . This is holding up developmen­ts that are essentiall­y shovel-ready. They could be generating jobs that are sorely needed in Northland, but instead they’re parked or being reconsider­ed due to unnecessar­y delays.”

Regional council consents manager Stuart Savill rejects the authority is “dragging its heels”.

The applicatio­ns were received between February 2018 and August 2019, with submission­s closing on November 1 last year.

Later that month the council discovered historic errors in its groundwate­r data — the water level under Houhora was 2.5m lower than previously thought — so bores had to be re-surveyed and models rerun with the new measuremen­ts.

The Covid-19 lockdown occurred during the same period, Savill said.

Two commission­ers had been appointed to consider the evidence and make a decision. They would hear 53 oral submission­s in Kaitaia from August 31 to September 4.

Northland businesses affected by the delays include Kaitaia-based Far North Roading, which has recently branched into avocado orchard developmen­t.

Managing director Manu Burkhardt-Macrae said the company would have to win other work or cut back its workforce of about 70 staff and 20 subcontrac­tors if the delays continued.

Further afield, Lynwood Avocado Nursery in Whanga¯ rei had already lost orders for 30,000 trees because of delays in the consenting process, founder Stephen Wade said.

With each cloned tree fetching about $50, the financial implicatio­ns were significan­t, and the company had already make five staff redundant due to the drop in orders.

The largest applicant in the

Aupo¯ uri Aquifer Water Users Group is Te Aupo¯ uri Commercial Developmen­t, the trading arm of Te Aupo¯ uri iwi, which has applied for an annual take of 1.17 million cu m to convert its 260ha beef farm into horticultu­re.

Those opposed to increased water take from the aquifer fear it could lead to salt water incursion, which would make bore water unusable.

Water campaigner Karyn NikoraKerr, of Ngataki, said the council shouldn’t even consider issuing new consents until the monitoring period for the last batch of consents was complete.

In 2018, the Environmen­t Court gave approval to 17 landowners, known as the Motutangi-Waiharara Water Users Group, to take up to 2 million cu m a year from the aquifer.

However, the approval was subject to raft of conditions, which included monitoring salinity, groundwate­r levels and wetlands over a nine-year period, and the initial water take was set at 0.5 million cu m.

Nikora-Kerr said the council should have followed the Environmen­t Court’s lead and rejected the latest applicatio­n until the monitoring period for the Motutangi-Waiharara consents, which has another seven years to run, was complete.

 ?? Photo / Peter de Graaf ?? The area around Houhora on the Aupo¯ uri Peninsula has seen a boom in avocado growing in recent years but growers say that’s threatened by uncertaint­y over water-use consents.
Photo / Peter de Graaf The area around Houhora on the Aupo¯ uri Peninsula has seen a boom in avocado growing in recent years but growers say that’s threatened by uncertaint­y over water-use consents.

Newspapers in English

Newspapers from New Zealand