The Post

$14m more to keep up motorway progress

- Thomas Coughlan thomas.coughlan@stuff.co.nz

The New Zealand Transport Agency (NZTA) will pay $14 million to the builders of Transmissi­on Gully as the beleaguere­d project looks to get back on track following the coronaviru­s crisis.

The $1 billion road is a publicpriv­ate partnershi­p between the transport agency, the contractor, Wellington Gateway Partnershi­p and the builder, CPB-HEB Joint Venture.

NZTA is currently negotiatin­g the full cost of Covid-19 on the project and the $14m payment is an advance interim payment on that final settlement.

The payment is meant to ensure work continues on the project over the winter while a final settlement is negotiated with contractin­g and constructi­on companies.

The road is likely to open some time next year.

NZTA transport services general manager Brett Gliddon said he was keen to keep work on the road going over the winter months.

‘‘We understand that people are keen to know when the road will be finished, and we are committed to seeing it open at the earliest possible date, and the winter works programme will help minimise further delays,’’ he said.

NZTA has managed to get Wellington Gateway and the builders to agree to a ‘‘winter constructi­on programme’’ that will keep people working on the project over the next six weeks while a new completion date is agreed to, along with costs.

‘‘However, Waka Kotahi [NZTA] must take a considered approach to making any decisions that involve taxpayer money and that is why an agreement on the new opening date and associated costs is taking time,’’ Gliddon said.

This isn’t the first additional payment the transport agency has made for Transmissi­on Gully.

Earlier this year the agency settled claims made by CPB-HEB over previous unavoidabl­e costs and delays, which saw the agency agree to pay an additional $190m. The opening deadline, already pushed back from April to May, was pushed back again to November 2020.

It’s now expected the road will not open until 2021 at the earliest.

Gliddon said the project was particular­ly hurt by the loss of valuable summer constructi­on time.

‘‘The Covid-19 stand-down period and subsequent work restrictio­ns has caused longer delays than the five weeks of level 4 due to the loss of valuable summer constructi­on and some of that work can’t be resumed until the weather improves again,’’ he said.

The winter works programme would ‘‘ensure the builder sources and brings onto site critical materials to allow the project to progress through the winter constructi­on season’’.

‘‘If materials, such as aggregate, are not sourced now there is a risk the materials may not be available later in the season.’’

Gliddon said reduced staff numbers at the site, which had been the subject of some speculatio­n, were a result of fewer staff being required over winter, and not related to Covid-19.

 ??  ??

Newspapers in English

Newspapers from New Zealand