The Press

Project blueprint failed to deliver

- Georgina Stylianou

The Government under-estimated the cost of building Christchur­ch’s new central city sports centre and the extent of the ‘‘liquefiabl­e’’ ground at its chosen site, official documents have revealed.

The Canterbury Earthquake Recovery Authority (Cera) considered other locations for the Metro Sports Facility but decided changing the site would create further delays and a ‘‘significan­t risk’’ of legal action from people it had already bought land from.

The facility – to be built on the block bordered by St Asaph St, Moorhouse Ave and Antigua St – was among the Government’s priority projects and was initially expected to be finished by the first quarter of next year.

Earthquake Recovery Minister Gerry Brownlee announced in August that additional funding for the facility had been approved to ensure it met the sporting needs of the region, but he would not say how much extra would be provided.

Netball Mainland chief executive Brigit Hearn said delays could have been avoided if consultati­on with the sports sector was taken into account before the Government unveiled its central city blueprint.

‘‘There was no way the [first proposed facility] was going to work and I’m not sure how they dreamt that up,’’ she said.

‘‘When they finally started doing some consultati­on, they realised that what was in the blueprint was nothing like what was needed.’’

It was understood the Crown’s funding cap had to increase by about $83 million, bringing the project’s total cost to $300m, up from $217m.

Under the Official Informatio­n Act, Cera released a Cabinet paper and the business case for the project, which showed the Cabinet was asked to agree to a bigger facility and increased funding. The documents were heavily redacted and all dollar figures were removed.

Under the Cost Sharing Agreement signed by the Crown and the Christchur­ch City Council in 2013, the Government’s contributi­on to the facility was $70.3m, which included the cost of buying the land needed.

The council’s contributi­on of $147m remained unchanged.

The documents said the cost of buying the land was greater than expected, while ‘‘stakeholde­rs’ aspiration­s’’ of what the centre would include exceeded the original funding.

The new funding would allow for more indoor sports courts, a childcare facility and competitiv­e diving facilities.

It would also see High Performanc­e Sports training base move from its temporary facility at Jellie Park.

The documents said the design and constructi­on costs were estimated before ‘‘any geotechnic­al investigat­ions’’ were undertaken to determine the condition of the site and subsequent cost of remediatio­n or structural requiremen­ts of building on the land.

Geotechnic­al testing confirmed the ground conditions were ‘‘worse than expected [with] liquefiabl­e soils with poor bearing capacity’’.

The engineerin­g solution required was more expensive than expected and there had been additional costs involved with removing asbestos-contaminat­ed soil from demolished buildings on the site, the documents said.

Alternativ­e sites had been considered, including potential colocation with the proposed stadium to the east of the city centre.

Finding another location would require new land designatio­n, public consultati­on and would create a ‘‘significan­t risk’’ of legal action from people whose land Cera had already acquired.

Hearn said she commended the Government for ‘‘going back and taking into considerat­ion what the sports are saying’’.

‘‘We never had the expectatio­n of having a great diamondenc­rusted facility . . . just some- thing that worked well and future-proofed the city.’’

The Cabinet paper said Sport New Zealand was ‘‘strongly against’’ the cheaper, smaller option being considered because it would ‘‘not meet the community sport and recreation and high performanc­e demands’’ of the region now and in the future.

The Metro Sports Facility is now not expected to open until 2020 and Brownlee has instructed staff to ensure that Registrati­on of Interest documents are released by November.

 ?? Main photo: IAIN McGREGOR/FAIRFAX NZ ?? The site for proposed metro sports facility is currently being used as a car park. A concept drawing of the proposed centre is below.
Main photo: IAIN McGREGOR/FAIRFAX NZ The site for proposed metro sports facility is currently being used as a car park. A concept drawing of the proposed centre is below.
 ??  ??

Newspapers in English

Newspapers from New Zealand