Expressway by the numbers

- Jo Lines-MacKenzie jo.lines-mackenzie@stuff.co. nz

There are some big numbers hidden in the concrete, steel and paint of the Hamilton section of the Waikato Expressway.

The 22km stretch is the final piece in the 102km four-lane highway that’s expected to reduce travel time between Auckland and Tīrau by 35 minutes.

It’s also expected to significan­tly reduce the number of fatal and serious injury crashes.

The section of road will be officially blessed on July 12 and opened soon after.

Here are some key numbers to reflect on when you drive it for the first time.

5,500,000

There have been 5.5 million cubic metres of earth moved. Earthworks generally happened in the summer months with the drier weather – however a wet summer in 2016 was one of the reasons the original completion date was pushed back.

110,000

Asphalt, some 110,000 tonnes of it, was used for the final surface of the road. Most of it was produced from a temporary asphalt plant on site that could produce 140 tonnes an hour. The approximat­e cost of the plant was $4 million and was put on leased land near the Ruakura Interchang­e.

Three gullies covering 10 hectares were restored in the road’s constructi­on. Native bats were monitored while fish and lizards were relocated into a ‘‘lizard hotel’’, a pest-protected enclosure east of Hamilton, before being released back into the gullies.

There are 16 bridges on the Hamilton section, 15 of those are concrete and one steel. All bridges were built to survive a 1-in-2000 year earthquake. The tallest bridge is Kay Rd which is 18.8 metres above ground. The longest is Mangaonua bridge at 150m long, which also has the deepest piles at 50m.

Drivers will be able to travel at 110kph on the expressway between Hampton Downs and south of Cambridge. It means people will be able to safely travel a continuous 78km at the increased speed. There are only two pieces of road in New Zealand

with 110kph signs.

There have been 7500 people inducted on to the site over the build, including subcontrac­tors, excluding visitors. There were up to 600 people who worked on the section in the first few years. The contract was awarded in November 2015 to CityEdge Alliance, made up of Fletcher Constructi­on, Higgins, Beca, Coffey and Waka Kotahi, with Hick Bros a sub-alliance for earthworks.

1.8

A 1.8 hectare reserve was establishe­d at a site of cultural significan­ce in Tamahere. There’s an installati­on of artwork and storyboard­s along the route and iwi designs on bridge abutments. Bridges were also gifted iwi names.

There is 233km of white road marking on the Hamilton section, along with 63km of flexible wire rope, 16km of steel W-section barrier, and 7km of concrete barrier. There are 750 street lights and 700 signs – everything from overhead gantry signs, to destinatio­n and smaller directiona­l signs.

The cost of the Hamilton section of the Waikato Expressway is $837m.

 ?? ??
 ?? CHRISTEL YARDLEY/STUFF ?? The Hamilton section of the Waikato Expressway has 16km of steel W-section barriers and 750 street lights.
CHRISTEL YARDLEY/STUFF The Hamilton section of the Waikato Expressway has 16km of steel W-section barriers and 750 street lights.
 ?? ??
 ?? ??