Waikato Times

Ring road unwrapped

- Jo Lines-MacKenzie jo.lines-mackenzie@stuff.co.nz TURN TO PAGE 2

After nearly 40 years in the making, Hamilton’s ring road is complete and ready for action.

The final piece of the loop is the $63 million Wairere Drive extension which will be formally opened this morning.

Hamilton City Council’s general manager of developmen­t, Chris Allen, said it was one of three major projects to help motorists move around the city.

The completion of the Waikato Expressway next week will take trucks out of the city, moving more traffic onto the ring road that encircles the central city. Work has just begun on the third project: making the north-south corridor of Peachgrove Rd to Hukanui Rd a slower route which is safer for cyclists, pedestrian­s and public transport.

Allen said those who should see an immediate change in traffic levels would be residents and businesses in Cambridge Rd, who have had to deal with detoured traffic.

Originally, the new interchang­e on Cobham Drive was going to be a roundabout connection due to not having a firm timetable for growth in the Peacocke area.

‘‘But then Peacocke’s growth area started to get a bit of momentum, and we secured some funding from the Government to open up the Peacocke area and build the bridge, so we then changed plans to build a proper interchang­e

there,’’ Allen said. The enabling work began in 2017, which saw electrical cables and water pipes moved, along with relocating a stream and also gas relocation before the current contract could begin in 2018.

The constructi­on of the interchang­e, which has been done by Fulton Hogan, has seen Cobham Drive lifted 6 metres so Wairere Drive can go underneath, all while allowing traffic to continue to use State Highway 1/Cobham Drive. ‘‘By lifting Cobham Drive it allows Wairere Drive to seamlessly connect to the bridge to Peacocke when it is finished, mid-to-late 2023. It also enabled better walking and cycling facilities to be built into the projects,’’ Allen said.

He recognised Covid-19 was a ‘‘wrecking ball’’ for numerous projects around New Zealand and was part of the reason completing the interchang­e took about a year longer than planned. Other challenges included in 2019, having started constructi­on, remnants of bullets were found in the topsoil between Dey St and Cobham Drive due to the site housing ammunition factories during World War II.

‘‘It also used to be the old dump. Hamilton Gardens is built on an old dump – that was a challenge for us because we found a lot of asbestos and lots of stuff we didn’t know was there – so it has been a really challengin­g site to build it on.’’

Cobham Drive is SH1, so the project has been a partnershi­p between the council and Waka Kotahi, which has helped in the cost of the $63m build as 72% is contribute­d by the government through Waka Kotahi subsidies.

For project manager Hannah Woods, building with live traffic, on a stretch of SH1 that has about 35,000 vehicles on it daily, was a big challenge.

‘‘We had a commitment to Waka Kotahi to keep two lanes

‘‘I and others ran a petition which achieved 10,000 signatures, so 38 years later we are finally there.’’ Councillor Martin Gallagher

into the city and one lane out open the entire time, so it has kept the site very constraine­d in terms of how we can build it.’’

Another limitation was the road could not be closed during the day.

‘‘So the only time we could do a lot of the work in the tie-in areas where the ramps come in and do all the asphalting on live lanes was on night shift.’’

But when she looks at the end result Woods is pretty pleased.

‘‘I am really proud of how it has all come together – especially the last three months it has been the most accelerate­d portion of the contract’’.

Hamilton city councillor Martin Gallagher said he was part of an original group opposed to diverting state highway traffic down Galloway, Peachgrove and Hukanui roads, which resulted in the ring road coming to be.

‘‘I and others ran a petition which achieved 10,000 signatures, so 38 years later we are finally there.’’

However, while pleased with the project, Gallagher wants to see even more progress when it comes to safer transport corridors.

‘‘We must now use this opportunit­y to focus back on those major residentia­l school streets in the Hamilton East area, to make sure they are safe for kids.

‘‘It is a personal pleasure to be involved in a big team that has brought this ring road to fruition, I think it transforms along with the expressway our transport patterns in Hamilton.’’

 ?? ?? Hamilton City Council’s Chris Allen and Hannah Woods say the final section of the ring road has offered up plenty of challenges.
Hamilton City Council’s Chris Allen and Hannah Woods say the final section of the ring road has offered up plenty of challenges.
 ?? MARK TAYLOR/STUFF ?? Hamilton’s ring road is completed and will aim to take thoroughfa­re traffic around the city rather than through it.
MARK TAYLOR/STUFF Hamilton’s ring road is completed and will aim to take thoroughfa­re traffic around the city rather than through it.
 ?? ?? Cobham Drive has been lifted 6 metres to allow Wairere Drive to run underneath.
Cobham Drive has been lifted 6 metres to allow Wairere Drive to run underneath.
 ?? ??

Newspapers in English

Newspapers from New Zealand