Weekend Herald

Spoke in the works: Victoria St cycleway will miss deadline

- Bernard Orsman

The $5.3 million Victoria St cycleway — part of roadworks reducing the city centre to a standstill — is running behind schedule.

Auckland Transport yesterday admitted it had failed to meet the deadline to complete the first, most disruptive, stage of the cycleway by the end of February.

Automobile Associatio­n spokesman Barney Irvine said any significan­t delay would tip a lot of people over the edge.

“If there are delays, we just hope that they’re kept to an absolute minimum, and that AT and council make up for them by managing the works much more effectivel­y in other parts of the CBD,” he said.

The news came on the same day O¯ra¯kei councillor Desley Simpson warned AT there would be “hell to pay” if traffic was disrupted on a $14.4m cycleway project about to begin on Tamaki Drive.

Simpson said she had an assurance from AT that traffic would flow normally at peak hours by operating two lanes into the city during the morning peak and two lanes to the east during the evening peak. Outside peak times,

If there are delays, we just hope that they’re kept to an absolute minimum, and that AT and council make up for them [elsewhere] . . .

AA spokesman Barney Irvine

single lanes will operate.

Nearly 40 road closures relating to roadworks are causing headaches for motorists and public transport users.

The Victoria St cycleway and longrunnin­g roadworks on Quay St are the two of the most visible disruption­s, earning Auckland the nickname “City of Cones”.

AT spokesman Mark Hannan said 80 per cent of the physical works would be completed on the Victoria St cycleway by the end of this month, including almost all work on the Victoria Park side of the road. Work on the Victoria Park Market side of the road would happen after February, but he did not give a date for completion. AT still aimed to have all three stages done by the middle of the year, he said.

Hannan said AT was on schedule to reopen the road lanes on Victoria St West by March 1 when the Wellesley St intersecti­on with Albert St and Mayoral Drive is closed.

The closure of the major intersecti­on for the best part of a year is for work to begin on a new undergroun­d rail station as part of the $4.4 billion City Rail Link.

The plan is to divert a lot of traffic from Wellesley St to Victoria St.

Newspapers in English

Newspapers from New Zealand