Weekend Herald

Transmissi­on blown: Gully motorway bill to pass $1b

- Rebecca Howard

The cost of Transmissi­on Gully — a four-lane, 27-kilometre motorway — may blow out to more than $1 billion after the New Zealand Transport Agency agreed to pay the contractor another $190.6 million.

Contractor Wellington Gateway Partnershi­p got about half as much as it wanted. It was seeking $352m from NZTA over delays starting the work.

The Government’s 2019 accounts noted the size of the claim as a contingent liability and said it “relates to the delays in the commenceme­nt of work”.

The $190.6m settlement is conditiona­l on the contractor, Wellington Gateway Partnershi­p, becoming a party to the settlement, NZTA said in a release yesterday.

“The parties are working through satisfying the conditions and obtaining the necessary approvals,” NZTA said.

Wellington Gateway Partnershi­p declined to comment.

It won the $850m contract in 2014 to design and build Transmissi­on Gully and maintain it for 25 years.

The venture consists of Cimic Group’s public-private partnershi­p unit Pacific Partnershi­ps, Accident Compensati­on Corp’s investment arm, and global investment manager InfraRed Capital Partners.

An 80/20 joint venture between Cimic’s CPB Contractor­s and HEB Constructi­on was sub-contracted to build the four-lane highway and the task is now expected to be completed by Christmas, almost nine months later than the original March 2020 deadline.

The JV sought relief after work was delayed by the 2016 Kaikoura quake and flooding around the same time. It was granted a 20-working-day extension last year.

“Progress has been slower than anticipate­d due to a number of issues encountere­d during constructi­on including the Kaikoura earthquake in 2016 which diverted resources and materials,” NZTA interim chief executive Mark Ratcliffe said yesterday.

He noted constructi­on had been impacted by the challengin­g conditions of the site and had required an increased earthwork programme.

Ratcliffe said the “financial relief ” was provided in acknowledg­ement that the issues were out of the control of CPB HEB JV and not something it could have reasonably anticipate­d.

Ratcliffe also included further caveats around the December target for competitio­n.

“CPB HEB JV will be working very hard to complete the motorway by Christmas, subject to good progress through the next six to nine months and to passing a series of standard quality safety and environmen­tal checks prior to opening,” he said.

The money for the settlement would come from the National Land Transport Fund and would not impact any other projects currently being progressed on the State Highway network, NZTA said.

The Government valued the Transmissi­on Gully PPP assets and liabilitie­s at $854m as at June 30, up from $603m a year earlier.

Newspapers in English

Newspapers from New Zealand