Daily Trust Saturday

‘Dadin Kowa power plant ready October’

- Haruna Gimba Yaya, Gombe Ibrahim Musa Giginyu, Kano

The Dadin Kowa Dam 40MW hydroelect­ric power plant will commence power supply by October, the firm handling the project, Mabon Nigeria Limited has said.

The project coordinato­r, Mr Cyril Christophe­r, disclosed this at the project site yesterday when the acting Director-General, Infrastruc­ture Concession Regulatory Commission (ICRC) Engineer Chidi Azuwah led management of the commission on a monitoring visit.

Mr Christophe­r said civil works had reached 85 per cent completion­adding that the company would accelerate work Nigeria Erosion and Watershed Management Project (NEWMAP) in collaborat­ion with Kano State government with support from the World Bank yesterday signed the engagement of an engineerin­g design consultanc­y firm for four water conservati­on structures and minor irrigation facilities.

They are to be constructe­d in Tofa, Shanono, Makoda and Takai local government areas of the state.

Speaking at the ceremony, NEWMAP state project coordinato­r, Malam Musa Shu’aibu, stated that the execution of the project under NEWMAP was in line with the provisions of project component document.

The Commission­er for Environmen­t, Alhaji Ali Haruna Makoda represente­d by the permanent secretary, Malam Baba Halilu Dantiye, revealed that the state government would continue to offer its support to see that the project succeeds. to make it ready for commission­ing by October.

Earlier, Engineer Izuwah said water release from Dadin Kowa would also make sustainabl­e power generation at Kiri Dam possible, adding that the project was a pathfinder and of double benefit to the North East geo-political zone.

NEWMAP to construct 4 water conservati­on facilities