70% of Ogoni clean-up to be completed August – Ministry

- Chidimma C. Okeke

Seventy per cent of the first phase of contract work on the Ogoni clean-up exercise is expected to be completed by the end of August 2020 while the other 30 per cent is expected to be finalized by the end of November, the Federal Ministry of Environmen­t has said.

A paper; “Ogoni Clean-Up: Achievemen­ts in Three Years,” released by the Ministry’s Director of Press, Mohammed Al-Sagir, said the 21 contractor­s who are at various stages of the remediatio­n processes had continued to achieve tremendous success despite delays caused by inclement weather, terrain, and community issues.

In 2018, procuremen­t processes commenced for remediatio­n of the Ogoni clean-up in line with the Public Procuremen­t Act of 2007.

Some more remediatio­n sites were handed over to 29 contractor­s in February 2020 and the Hydrocarbo­n Pollution Remediatio­n Project (HYPREP) HYPREP had commenced to enable contractor­s access remediatio­n site and commence operations

HYPREP has also carried out a survey of the water reticulati­ng distances in the four LGAs for the supply of potable water in the communitie­s, Mohammed said.

“Ten existing water schemes will be rehabilita­ted across the four LGAs and are expected to supply about 10,950,000 litres of water per day to the communitie­s. We are also in the process of engaging consultant­s to carry out detailed design for new water scheme in Ogoniland. The tendering processes are ongoing,” the paper said.

 ?? PHOTO NAN ?? Sympathise­rs queue to enter to the residence of the former Governor of Oyo state, late Sen. Abiola Ajimobi, Oluyole, Ring Road in Ibadan, yesterday.
PHOTO NAN Sympathise­rs queue to enter to the residence of the former Governor of Oyo state, late Sen. Abiola Ajimobi, Oluyole, Ring Road in Ibadan, yesterday.

Newspapers in English

Newspapers from Nigeria