Daily Trust

Mambilla power project gets $5.79bn for takeoff

-

the contract today to joint ventures of Chinese Civil and Engineerin­g Company for the engineerin­g and turn-key contract, including civil and electro-mechanical works for 5.792 billion dollars. The constructi­on should take about 72 months (6 years).

“It is designed to deliver 3,050 megawatt of power. The productive output will be a function of water supply, because that is the major source of fuel, is a hydroplane.”

Fashola added: “The project requires the constructi­on of four dams, one of them is about 150 meters in height, the immediate two are 70 meters in height and the smallest of them is 50 meters in height.

“It also includes 700 kilometres of transmissi­on line. It will be in Taraba state in the area called Gembu, and it will unleash the potential that have been reported about Mambila, including agricultur­e, tourism and energy.

“You will recall that sometimes last year, the Chinese government held a summit in South Africa, essentiall­y what that was about was supporting and partnering with African government to do their infrastruc­ture and also funding the Agurua projects, so this was one of the projects of infrastruc­ture that was submitted there and I think it also had the rail component.

“The money is coming from the Chinese government through their Exim bank, so it is an export funding support for them and an import funding for us. Eighty five percent is supposed to be financed by them and 15 per cent is our own counterpar­t funding.

“The award now triggers contract negotiatio­ns for the financing side and after that are concluded the projects can now start.”

(Buhari’s aide, Garba Shehu, writes on Mambilla power project on page 46>>>)