TCN completes over 18 transmissi­on projects, adds 1,100mw to grid

- By Simon Echewofun Sunday

The Transmissi­on Company of Nigeria (TCN) has completed and is ready to commission over 18 high voltage transforme­rs to help evacuate 1,100 megawatts (MW ) of electricit­y to the national grid by January 2018.

The Interim Managing Director of the Transmissi­on Company of Nigeria (TCN), Mr Usman Gur Mohammed disclosed this yesterday during a tour of some of the substation­s in Apo and Katampe in Abuja and Suleja in Niger state.

Mohammed said the projects completed and being commission­ed from December 2017 to the end of January 2018 after which it will begin to re-conduct transmissi­on lines to ensure the added power capacities are evacuated after the first quarter of next year.

He noted that the projects being executed under the Transmissi­on Rehabilita­tion and Expansion Programme (TREP) which seeks to expand the grid to 20,000MW in the next four years.

“In line our strategy, are completing across the country several projects which would cumulative­ly add over 1,000mw transforme­r capacity to the grid before January 31, 2018. The Nigerian Electricit­y Transmissi­on Access Project (NETAP) which is one of the projects under REP was successful­ly negotiated and finalised with the World Bank on December 8,” he explained.

Mohammed lauded the company for wheeling the highest peak generation of 5,155mw recently saying, “We must work towards a national peak of 6,000mw in the early part of next year.” are with we