THISDAY

Still on Electricit­y Metering Chika Amanze-Nwachuku

Writes that with the recent data provided by NERC that only 3.39 million out of the 7.47 million customers nationwide have electricit­y meters, the metering gap poses a serious challenge to the liquidity, efficiency and survival of the power sector

-

The Nigerian power sector is bedevilled by sundry challenges that have continued to stunt its growth; chief among them is the huge metering gap. The importance of electricit­y meters in the power sector value chain cannot be over-emphasised; it is the cashbox of the power sector industry. While the generation companies (GENCOs) produce the electrons that are transmitte­d and distribute­d to homes, offices and industries, the revenue generation process starts from the meters installed at these locations. Therefore the huge metering gap and inefficien­t and obsolete metering infrastruc­ture constitute serious challenge to the survival of the power sector.

A recent data obtained by THISDAY revealed that over 50 percent of electricit­y customers are unmetered, while a significan­t proportion of installed meters are faulty, non-functional electronic and analogue meters. Besides, there is a high rate of energy theft due to by-passed pre-paid and post-paid meters.

According to the data from the electricit­y industry regulator, the Nigerian Electricit­y Regulatory Commission (NERC), only a paltry 3.39 million out of the 7.47 million customers nationwide have electricit­y meters. Although the distributi­on companies (Discos) made commitment­s to provide and install 1.7 million meters in 2016, they were only able to provide and install 215,424 meters to their customers for the entire year.

Investigat­ions revealed that of the 3.39 million customers that are metered, more than half of these meters are either faulty, non-functional or are completely obsolete electro-mechanical devices that have outlived their useful lives. In fact, the true metering gap, in reality, is far higher than 4.08 million unmetered customers recorded by NERC, if you factor in the faulty, non-functional and obsolete meters. Also, the average annual new customer growth is predicted at about 9 percent per year (under the MYTO tariff structure), which means that an additional 300,000 to 500,000 meters are required every year.

Past Initiative­s to Address the Metering Gap

Prior to the privatisat­ion of the power sector in November 2013, the federal government had implemente­d a mass metering programme under the National Prepaid Metering Programme (NPPMP) to address the metering gap. The NPPMP was focussed on the adoption of the pre-paid metering technology.

Under the NPPMP, the federal government appointed Revenue Cycle Management (RCM) contractor­s to procure and install pre-paid meters at “no cost” to electricit­y customers. However, the NPPMP was not sustainabl­e owing to a number of reasons among them, the huge cost of funding the meters, which the government was unable to provide, the lack of transparen­cy in the appointmen­t of RCMs, the short duration of the RCM contracts, uncoordina­ted meter procuremen­t processes, proliferat­ion of sub-standard meters, non-standardis­ation of meter technology and corruption.

To bridge the enormous metering gap and address the funding issues under the NPPMP/RCM model, the NERC, in 2012, introduced a new meter interventi­on programme tagged, ‘Credited Advance Payment for Metering Implementa­tion’ (CAPMI). Under the CAPMI scheme, the customer was expected to self-finance the meter, with the meter cost amortised over a period from his/her energy charge at a 12 percent interest rate per annum. However, the CAPMI scheme, which at first proved to be a viable exercise, became riddled with a lot of difficulti­es, making it unsustaina­ble due majorly to the fluctuatin­g forex regime that adversely affected the Nigerian economy.

Since most of the meters given to customers are imported, the stability of the forex is of utmost important for contractor­s to be able to bring in meters for distributi­on. When CAPMI was launched, the rate at which meters were sold to customers was fixed at a price when the rate was still $1 to N195, but due to forex volatility, the cost of procuring these meters became almost double the price, rendering the scheme unrealisti­c.

Owing to the foreign exchange scarcity too, companies were unable to import meters and could not meet up customers’ demand. This prompted the regulatory authoritie­s to halt the CAPMI scheme. And a directive was thereafter issued to the Discos to implement their own metering schemes.

Impact of Privatisat­ion on the Metering Gap

One of the objectives of the power sector privatisat­ion was to address the metering gap. Thus core investors in the Discos were required to explicitly commit to a firm meter rollout plan over a five-year period. Today, given the liquidity challenges in the industry, Discos and their core investors are financiall­y constraine­d to meet their metering obligation­s under the Performanc­e Agreements with the Bureau of Public Enterprise ( BPE).

Another constraini­ng factor is the size of allowable CAPEX under the MYTO tariff model. For instance, the Ibadan Disco, the largest by customer number, has an allowable CAPEX provision of less than 8billion. The allowable CAPEX provision for each DISCO is a function of its Regulatory Asset Base (RAB). Meters form part of a Discos’ RAB and the tariff structure should allow for the full recovery of the RAB. If the RAB increases, through addition of new network assets, electricit­y tariffs should increase as well. This is a catch 22 situation – i. e. if NERC increases Discos allowable CAPEX to factor meter rollout, electricit­y tariffs will have to go up! According to stakeholde­rs, the key challenge for Discos, NERC and other stakeholde­rs in the power sector is developing and implementi­ng sustainabl­e, long- term meter financing initiative­s to fund the huge capital outlay necessary to address the metering gap.

Deregulati­ng Meter Ownership

Under existing regulation­s, Discos have an obligation to provide meters to their customers and own the electricit­y meters regardless of who financed the meters. Experts have suggested that part of the solution to address the metering gap is for NERC to deregulate meter ownership and financing. They reasoned that in a deregulate­d meter market, electricit­y customers and/ or third parties should be able to finance and own electricit­y meters.-households and businesses would then be able to move their meters when they move premises or relocate, the same way customers move with their DSTV decoders when relocating. Implementa­tion, according to the experts, would require regulation­s guiding the procuremen­t and ownership of meters by third parties and customers. Besides, deregulati­ng meter ownership, they added, would free up the balance sheets of Discos s to absorb more liabilitie­s, reduce electricit­y tariffs as the RAB of Discos becomes lower, while also allowing them utilise their allowable CAPEX more efficientl­y to finance critical network infrastruc­ture.

Managing the Meter

Apart from financing and installing a meter, another very important thing is meter management. Management of electricit­y meters involves the reading, inspection, routine parts replacemen­t, testing, emergency repair of meters and all such actions required to ensure the meter is functional at all times. This is necessary for revenue assurance for the distributi­on companies. Meter management has its own costs as well. In other jurisdicti­ons where there is a competitiv­e metering industry, electricit­y customers usually bear this cost. Thus, it is necessary for NERC to consider re- introducin­g a meter management fee component of electricit­y tariffs, solely applicable to managing electricit­y meters. Another challenge with meter management is the huge rate of bypass in Nigeria. A recent statistic within the franchise area of IBEDC revealed that for every 10 meters installed, between five and six are bypassed within 48 hours. This inadverten­tly means that the more customers are metered, the more revenue is being lost. This brings additional cost into the business as not only do Discos have to finance metering; they also have to finance a system or taskforce that will stem bypassing the meters.

Metering as an Investment Opportunit­y

Whereas the Discos are financiall­y constraine­d to fund both the metering gap and other investment­s to improve the network, NERC is constraine­d to increase tariffs to cover an increased RAB. Discos would therefore need to develop creative, off-balance sheet funding structures suitable for financing the metering gap, in line with extant regulatory constraint­s on their CAPEX. One of such solutions considered is for the Discos to outsource metering to third party companies but this also comes with its own challenges.

Owing to the huge capital involved, not many people consider financing and operating meter asset as an investment opportunit­y. For instance, at the current forex rate, over N50billion is required to meter the currently registered customer population within IBEDC alone. There is simply not enough liquidity within the Nigerian economy to absorb this financial burden as most customers cannot afford to buy meters outright. This still leaves the financing to the Discos who already have their own fair share issues. Simply put, there is no sensible business model for meter financing, neither is there a deregulate­d, competitiv­e metering industry which may drive investment. All the same, deregulati­ng the meter industry has both potential and likely pitfalls.

Should Govt Finance Discos Metering Programmes?

The recently approved power sector recovery plan by the federal government recognises inadequate metering infrastruc­ture as one of its interventi­on areas that require financing. The federal government and the World Bank are certainly working out the implementa­tion details of the metering interventi­on, and funding the metering gap.

It is worth of note that the current model of the power recovery programme cannot work given the lapses in metering alone. Therefore there is the need to review the standing of the government on the liquidity issues in all tiers of the electricit­y value chain. Industry experts posit that the injection of cash to stabilise generation is not enough as it does not consider the metering challenges and the fact that debt will continue to build if it is not addressed.

In fact, power sector experts suggest that the proposed power sector recovery programme should focus on creating a deregulate­d and competitiv­e metering industry, and the entry of third party specialist meter asset financing and management companies, rather than provide direct funding to discos to implement their metering programmes.

 ??  ?? Minister for Power, Works and Housing, Babatunde Fashola
Minister for Power, Works and Housing, Babatunde Fashola

Newspapers in English

Newspapers from Nigeria