Outage: Katsina, TCN Sign MoU to Boost Power Supply

- Francis Sardauna

In a bid to enhance power supply in Katsina State, the State Government and the management of Transmissi­on Company of Nigeria (TCN) have signed a Memorandum of Understand­ing (MoU) for the constructi­on of 2x60 MVA transmissi­on sub-power station in Mashi Local Government Area of the state.

Speaking during the signing of the memorandum, Governor Aminu Bello Masari, lamented that the state was experienci­ng acute power outage due to numerous uncomplete­d power projects in the state.

Masari, in a statement from his Director General, Media and Publicity Friday, Abdu Labaran Malumfashi, urged TCN to complete the constructi­on of 2x 60 MVA Sheme-Gusau power station and ensure the extension of the 132 DC transmissi­on line from Daura to Kazaure in Jigawa state to improve power supply in the two states.

He said: “An investor is allocated with a land in Sheme village for the establishm­ent of a textile factory but because of the pending power project, he is there waiting. So, the completion of the electricit­y project will enable him to commence work on his textile factory and as well boost power and economic activities in the state.

“Therefore, I urge you to bring designs as it affects the right of way to ascertain whether it involves movement of the communitie­s so that compensati­on could be sought for residents of such communitie­s.”

Earlier, the representa­tive of TCN, Bashir Hassan, told the governor that the projects if competed will generate power from Kano station to Katsina through Daura.

He added: “Daura has an existing station, so the circle will bring power supply from Kano to Katsina, Daura to Danbatta to Babura and a 2x40 sub station in Daura is already being fed with 80 megawatt from Katsina sub station.

On his part, the principal Manager in charge of Lines, Engineer Ibrahim Aliyu, explained that TCN had completed payment of compensati­on for land in Batagarawa while efforts are in progress to pay the compensati­on in Kusada.

Engineer Ibrahim Aliyu explained that constructi­on of electricit­y towers on Kano to Bichi line had been completed , adding that conductors and auxiliary readings have been completed too.

He said work on Katsina-Kurfi-Dutsinma-Kankara-Malumfashi line has temporaril­y stopped due to funding problem, as it will be executed with internally generated revenue of TCN instead of Appropriat­ion..